Differences between revisions 14 and 15
Revision 14 as of 2017-12-14 14:03:41
Size: 1598
Comment:
Revision 15 as of 2017-12-14 14:04:54
Size: 1805
Comment:
Deletions are marked like this. Additions are marked like this.
Line 33: Line 33:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])  * Meeting for pump down at ETMY ([[KAGRA/Commissioning/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * Meeting for closing ETY ([[KAGRA/Commissioning/Meetings/Others/20171117|Minute]])

Stage 1

  • Alignment up to BS


Stage 2

  • Align ETMy to IFI (MIF, DGS, VIS, CRY, IOO) with damping
  • Lead MI-REFL beam outside the chamber (MIF, IOO)
  • Install and align MI-REFL output optics using the beam reflected by ETMy (MIF)


Preparation

  • Oplev: 準備は進んでいる。(阿久津)
  • Actuator: 動かせるようになっている。
  • Dampig: センサーの準備をしているところ。PDの光は見えている。
  • RT model:
  • ビームセンターはTcamで見る。
  • 透過光用にBRTはインストールするが、おそらくPhase1では見えない。
  • エンドの物品の準備 -> 和泉

  • 人員手配 -> MIF

Tasks

  • EYCのTypeAとPayload接続完了 (2017/12/1)

  • ETMYでの光確認
  • ETMYのアクチューエターの確認
  • BSのdampingの確認
  • ETMYのdampingの確認
  • ETMYからの光をセンターエリアで確認
  • REFLまでの引きこみ

Meetings

Check list


Stage 3

Tasks

  • Alignment of ETMx
  • Locking of MI with Cryogenic ETMy with Calibrated sensitivity curve


Stage 4

  • Locking of MI in vacuum with cryogenic ETMx/y with data stored


Test run

KAGRA/Commissioning/Phase1/Task (last edited 2018-05-24 11:21:22 by OsamuMiyakawa)