| == bKAGRA Phase2 == | = bKAGRA Phase2 = |
| Line 4: | Line 4: |
| ---- == Schedule == 2017/5/1 updated |
|
| Line 5: | Line 8: |
| {{attachment:KAGRA/Commissioning/Phase2/Chief180501_Phase2_schedule.png||width=1200}} ----- |
|
| Line 6: | Line 13: |
| * Target: High power laser * Term: 2018/5/7 ~ 2018/9 === Stage 2 === |
|
| Line 7: | Line 19: |
| * Term: 2018/10 ~ 2018/12? | |
| Line 13: | Line 26: |
| * Term: 2018/5/7 ~ 2018/12? | |
| Line 15: | Line 27: |
| === Stage 2 === | === Stage 3 === |
| Line 17: | Line 29: |
| * Term: 2018/12? ~ 2019/2? * Milestone |
|
| Line 23: | Line 37: |
| * Term: 2018/12? ~ 2019/2? | |
| Line 25: | Line 38: |
| === Stage 3 === | === Stage 4 === |
bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Schedule
2017/5/1 updated
Stage 1
- Target: High power laser
- Term: 2018/5/7 ~ 2018/9
Stage 2
- Target: X arm commissioning
- Term: 2018/10 ~ 2018/12?
- Milestone
- VIS ITMX
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
Stage 3
- Target: Y arm commissioning
- Term: 2018/12? ~ 2019/2?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
Stage 4
- Target: FPMI commissioning
Stage 4
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO