Differences between revisions 1 and 8 (spanning 7 versions)
Revision 1 as of 2018-05-08 08:53:02
Size: 661
Comment:
Revision 8 as of 2018-05-08 10:44:50
Size: 888
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
== bKAGRA Phase2 == = bKAGRA Phase2 =
Line 4: Line 4:
----
== Schedule ==
2017/5/4 updated
Line 5: Line 8:
{{attachment:KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png||width=1200}}


-----
Line 6: Line 13:
 * Target: High power laser
 * Term: 2018/5/7 ~ 2018/9


=== Stage 2 ===
Line 7: Line 19:
 * Term: 2018/10 ~ 2018/12?
Line 13: Line 26:
 * Term: 2018/5/7 ~ 2018/12?
Line 15: Line 27:
=== Stage 2 === === Stage 3 ===
Line 17: Line 29:
 * Term: 2018/12? ~ 2019/2?
 * Milestone
Line 23: Line 37:
 * Term: 2018/12? ~ 2019/2?
Line 25: Line 38:
=== Stage 3 === === Stage 4 ===

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/5/4 updated

KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png


Stage 1

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/9

Stage 2

  • Target: X arm commissioning
  • Term: 2018/10 ~ 2018/12?
  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 3

  • Target: Y arm commissioning
  • Term: 2018/12? ~ 2019/2?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 4

  • Target: FPMI commissioning

Stage 4

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO