2017/5/4 updated 2017/8/21 updated

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/8/21 updated

KAGRA/Commissioning/Phase2/Chief180821_Phase2_schedule.png


HPL stage

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/8/31

XA stage

  • Target: X arm commissioning
  • Term: 2018/9/1 ~ 2018/12?
  • Task list

  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

YA stage

  • Target: Y arm commissioning
  • Term: 2019/1? ~ 2019/3?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

FPMI stage

  • Target: FPMI commissioning
  • Term: 2019/3? ~ 2019/4?

RSE stage

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO

KAGRA/Commissioning/Phase2/Task (last edited 2018-08-21 15:12:17 by OsamuMiyakawa)