Differences between revisions 2 and 10 (spanning 8 versions)
Revision 2 as of 2018-05-08 09:21:11
Size: 752
Comment:
Revision 10 as of 2018-05-22 09:08:39
Size: 928
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
== bKAGRA Phase2 == = bKAGRA Phase2 =
Line 4: Line 4:
----
== Schedule ==
2017/5/4 updated
Line 5: Line 8:
=== Stage 1 ===
 * Target: High power laser
 * Term: 2018/5/7 ~ 2018/9
{{attachment:KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png||width=1200}}
Line 10: Line 11:
=== Stage 2 === -----
=== HPL stage ===
 * Target: High power laser
 * Term: 2018/5/7 ~ 2018/8/31


=== XA stage ===
Line 12: Line 19:
 * Term: 2018/10 ~ 2018/12?  * Term: 2018/9/1 ~ 2018/12?
Line 20: Line 27:
=== Stage 3 === === YA stage ===
Line 22: Line 29:
 * Term: 2018/12? ~ 2019/2?  * Term: 2019/1? ~ 2019/3?
Line 31: Line 38:
=== Stage 4 === === FPMI stage ===
Line 33: Line 40:
 * Term: 2019/3? ~ 2019/4?
Line 34: Line 42:
=== Stage 4 === === RSE stage ===

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/5/4 updated

KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png


HPL stage

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/8/31

XA stage

  • Target: X arm commissioning
  • Term: 2018/9/1 ~ 2018/12?
  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

YA stage

  • Target: Y arm commissioning
  • Term: 2019/1? ~ 2019/3?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

FPMI stage

  • Target: FPMI commissioning
  • Term: 2019/3? ~ 2019/4?

RSE stage

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO

KAGRA/Commissioning/Phase2/Task (last edited 2018-08-21 15:12:17 by OsamuMiyakawa)