== bKAGRA Phase2 == | = bKAGRA Phase2 = |
Line 4: | Line 4: |
---- == Schedule == 2017/5/4 updated |
|
Line 5: | Line 8: |
=== Stage 1 === * Target: High power laser * Term: 2018/5/7 ~ 2018/9 |
{{attachment:KAGRA/Commissioning/Phase2/Chief180821_Phase2_schedule.png||width=1000}} |
Line 10: | Line 11: |
=== Stage 2 === | ----- === HPL stage === * Target: High power laser * Term: 2018/5/7 ~ 2018/8/31 === XA stage === |
Line 12: | Line 19: |
* Term: 2018/10 ~ 2018/12? | * Term: 2018/9/1 ~ 2018/12? * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit#gid=0|Task list]] |
Line 15: | Line 23: |
* [[/CheckList/VacuumITMX|Check list]] for ITMX closing | |
Line 20: | Line 29: |
=== Stage 3 === | === YA stage === |
Line 22: | Line 31: |
* Term: 2018/12? ~ 2019/2? | * Term: 2019/1? ~ 2019/3? |
Line 31: | Line 40: |
=== Stage 4 === | === FPMI stage === |
Line 33: | Line 42: |
* Term: 2019/3? ~ 2019/4? | |
Line 34: | Line 44: |
=== Stage 4 === | === RSE stage === |
bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Schedule
2017/5/4 updated
HPL stage
- Target: High power laser
- Term: 2018/5/7 ~ 2018/8/31
XA stage
- Target: X arm commissioning
- Term: 2018/9/1 ~ 2018/12?
- Milestone
- VIS ITMX
Check list for ITMX closing
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
- VIS ITMX
YA stage
- Target: Y arm commissioning
- Term: 2019/1? ~ 2019/3?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
FPMI stage
- Target: FPMI commissioning
- Term: 2019/3? ~ 2019/4?
RSE stage
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO