Line 12: | Line 12: |
=== Stage 1 === | === HPL stage === |
Line 14: | Line 14: |
* Term: 2018/5/7 ~ 2018/9 | * Term: 2018/5/7 ~ 2018/8/31 |
Line 17: | Line 17: |
=== Stage 2 === | === XA stage === |
Line 19: | Line 19: |
* Term: 2018/10 ~ 2018/12? | * Term: 2018/9/1 ~ 2018/12? |
Line 27: | Line 27: |
=== Stage 3 === | === YA stage === |
Line 29: | Line 29: |
* Term: 2018/12? ~ 2019/2? | * Term: 2019/1? ~ 2019/3? |
Line 38: | Line 38: |
=== Stage 4 === | === FPMI stage === |
Line 40: | Line 40: |
* Term: 2019/3? ~ 2019/4? | |
Line 41: | Line 42: |
=== Stage 4 === | === RSE stage === |
bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Schedule
2017/5/4 updated
HPL stage
- Target: High power laser
- Term: 2018/5/7 ~ 2018/8/31
XA stage
- Target: X arm commissioning
- Term: 2018/9/1 ~ 2018/12?
- Milestone
- VIS ITMX
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
YA stage
- Target: Y arm commissioning
- Term: 2019/1? ~ 2019/3?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
FPMI stage
- Target: FPMI commissioning
- Term: 2019/3? ~ 2019/4?
RSE stage
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO