Line 14: | Line 14: |
* Term: 2018/5/7 ~ 2018/9 | * Term: 2018/5/7 ~ 2018/8/31 |
Line 19: | Line 19: |
* Term: 2018/10 ~ 2018/12? | * Term: 2018/9/1 ~ 2018/12? |
Line 29: | Line 29: |
* Term: 2018/12? ~ 2019/2? | * Term: 2019/1? ~ 2019/3? |
Line 40: | Line 40: |
* Term: 2019/3? ~ 2019/4? | |
Line 41: | Line 42: |
=== Stage 4 === | === Stage 5 === |
bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Schedule
2017/5/4 updated
Stage 1
- Target: High power laser
- Term: 2018/5/7 ~ 2018/8/31
Stage 2
- Target: X arm commissioning
- Term: 2018/9/1 ~ 2018/12?
- Milestone
- VIS ITMX
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
Stage 3
- Target: Y arm commissioning
- Term: 2019/1? ~ 2019/3?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
Stage 4
- Target: FPMI commissioning
- Term: 2019/3? ~ 2019/4?
Stage 5
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO