Line 14: Line 14:
 * Term: 2018/5/7 ~ 2018/9  * Term: 2018/5/7 ~ 2018/8/31
Line 19: Line 19:
 * Term: 2018/10 ~ 2018/12?  * Term: 2018/9/1 ~ 2018/12?
Line 29: Line 29:
 * Term: 2018/12? ~ 2019/2?  * Term: 2019/1? ~ 2019/3?
Line 40: Line 40:
 * Term: 2019/3? ~ 2019/4?
Line 41: Line 42:
=== Stage 4 === === Stage 5 ===

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/5/4 updated

KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png


Stage 1

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/8/31

Stage 2

  • Target: X arm commissioning
  • Term: 2018/9/1 ~ 2018/12?
  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 3

  • Target: Y arm commissioning
  • Term: 2019/1? ~ 2019/3?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 4

  • Target: FPMI commissioning
  • Term: 2019/3? ~ 2019/4?

Stage 5

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO