Differences between revisions 9 and 10
Revision 9 as of 2018-05-08 10:47:13
Size: 919
Comment:
Revision 10 as of 2018-05-22 09:08:39
Size: 928
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
=== Stage 1 === === HPL stage ===
Line 17: Line 17:
=== Stage 2 === === XA stage ===
Line 27: Line 27:
=== Stage 3 === === YA stage ===
Line 38: Line 38:
=== Stage 4 === === FPMI stage ===
Line 42: Line 42:
=== Stage 5 === === RSE stage ===

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/5/4 updated

KAGRA/Commissioning/Phase2/Chief180504_Phase2_schedule.png


HPL stage

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/8/31

XA stage

  • Target: X arm commissioning
  • Term: 2018/9/1 ~ 2018/12?
  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

YA stage

  • Target: Y arm commissioning
  • Term: 2019/1? ~ 2019/3?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

FPMI stage

  • Target: FPMI commissioning
  • Term: 2019/3? ~ 2019/4?

RSE stage

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO

KAGRA/Commissioning/Phase2/Task (last edited 2018-08-21 15:12:17 by OsamuMiyakawa)