2018/9/4 Commissioning meeting topics
- The first day of night work
- Preparation of Power outage on 9/10
- Task check for IXC installation and closing to vacuum
- Readiness for the X arm commissioning.
- Laser, PSL, IOO report
http://klog.icrr.u-tokyo.ac.jp/osl/?r=5970: Alignment to IMMT
http://klog.icrr.u-tokyo.ac.jp/osl/?r=5966: Positions of IMMTs
- DAC and BIO on IOO chassis
- Drift during pumping down
- ETMX damping