Minute of KAGRA commissioning meeting
- Date: 2018/10/23 11AM~12PM
- Attendance: Miyakawa, Izumi, Aso, Kozakai, Oshino, Kokeyama
- eZuce: Enomoto, Miyoki, Ushiba, Kimura
Schedule
- 10/25, leak check has a priority than commissioning work.
- 10/30, Inspection for cleanning need 30min, that is fine.
- We propose to submit an application for the work at the control room.
- Night shift in November needs some forceful assignment, additionally current volunteer based assignment.
X arm alignment
- X arm was locked with green. Longest lock is ~1hour order.
- ETMX has some motion ~few urad.
IOO
- 700mW is easy, but if more power is needed, please let IOO as fast as possible.
DGS
- Proposing Wednesday morning as a maintenance time.
- DGS group discusses maintenance items every week and announces them.
Others
- Next meeting: 10/30.