Minute of KAGRA commissioning meeting


  • Date: 2018/10/23 11AM~12PM
  • Attendance: Miyakawa, Izumi, Aso, Kozakai, Oshino, Kokeyama
    • eZuce: Enomoto, Miyoki, Ushiba, Kimura


Schedule

  • 10/25, leak check has a priority than commissioning work.
  • 10/30, Inspection for cleanning need 30min, that is fine.
  • We propose to submit an application for the work at the control room.
  • Night shift in November needs some forceful assignment, additionally current volunteer based assignment.

X arm alignment

  • X arm was locked with green. Longest lock is ~1hour order.
  • ETMX has some motion ~few urad.

IOO

  • 700mW is easy, but if more power is needed, please let IOO as fast as possible.

DGS

  • Proposing Wednesday morning as a maintenance time.
    • DGS group discusses maintenance items every week and announces them.

Others

  • Next meeting: 10/30.

KAGRA/Commissioning/Weekly/20181023/Minute (last edited 2018-10-23 12:18:04 by OsamuMiyakawa)