Line 10: | Line 10: |
* 11/5-end of Nov.: IYA root will be closed. | * Every Wednesday morning: Maintenance * 11/5-end of Nov.: Route to IYA is closed. |
Line 13: | Line 14: |
* MZ work needs stopping IR in the daytime; ~10/31 ok, 11/1~11/31? * Assignment of tuning for suspensions. |
2018/11/6 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
- Every Wednesday morning: Maintenance
- 11/5-end of Nov.: Route to IYA is closed.
- 11/6: AM or PM for 30min : Inspection for ETMX cleaning
- 12/10 or 11: ETMX cleaning
- X arm lock
- ETMX
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6752: damping loop engaged
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6725: ETMX TM H2 coil dones not respond
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6731: Broken magnet?
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6741: Image of ETMX
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6742: Image of ETMX
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6749: Image of ETMX
- Laser, PSL, IOO report
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6743: Broken AOM?
- OMC installation
- DGS
- Scheduling for maintenance time on Wednesday morning.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6732: picomotor