 * New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed. [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9311|Other list by Saito]].
  * Extended date: 12/10-1/6.
 
* 1/6: End of X arm commissioning -> Open chambers.
  * 1/18~ : Y arm alignment from BS to ETMY using IR beam.
  * 2/18~ Y arm commissioning
 * 1/6: End of X arm commissioning -> Open chambers.
 * 1/18~ : Y arm alignment from BS to ETMY using IR beam.
 * 2/18~ Y arm commissioning

2018/12/17 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance; 12/19: Check RFM for ITMs, changing RT PC etc.
  • 12/15, 16 and Week of 12/17~: No night work.
  • 1/6: End of X arm commissioning -> Open chambers.

  • 1/18~ : Y arm alignment from BS to ETMY using IR beam.
  • 2/18~ Y arm commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.