Differences between revisions 1 and 8 (spanning 7 versions)
Revision 1 as of 2018-12-17 17:56:40
Size: 1773
Comment:
Revision 8 as of 2018-12-18 10:51:28
Size: 2345
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * 12/15, 16 and Week of 12/17~: No night work.  * 12/17~: No night work.
 * 1/4-6: Removal of first contact of ETMY
 * 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
 * 12/21: laser stop in the morning.
 * 12/29,30: line injection.
 * 1/6: End of X arm commissioning.
 * 1/7~ : Opening EXC chamber.
 * 1/7~ : Hight check for VIS systems.
 * 1/17~ : Y arm alignment from BS to ETMY using IR beam.
Line 14: Line 22:
 * New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed. [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9311|Other list by Saito]].
  * Extended date: 12/10-1/6.
  * 1/6: End of X arm commissioning -> Open chambers.
  * 1/18~ : Y arm alignment from BS to ETMY using IR beam.
  * 2/18~ Y arm commissioning

 * beam alignment:
  * 1/7~: Opening IMC Chamber.
   * IMC beam alignment in air: 1/11-14
   * IMC lock recover in vacuum: 1/16
   * IMC to ETMX: 1/17-21
  * BS to ETMY: 1/17-21
  * ITMY to REFL: 1/21-22
  * ITMY to SRM: 1/22-23
  * ITMY to OMC: 1/23-25
  * ITMX to OMC: 1/23-25
  * POS to ETMY(Green laser): 1/23-24
  * ETMY to POS(Green laser): 1/24-25
  * ETMX to ITMX: 2/11-22

 * 2/4~ DRMI Y arm commissioning
 * 2/18~ Y arm commissioning
 * 3/18~ FPMI commissioning
Line 24: Line 46:
  * 12/18-28: CAL work at EXA
Line 44: Line 67:
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9523]]: Debuggin the scattered light problem.

2018/12/17 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance; 12/19: Check RFM for ITMs, changing RT PC etc.
  • 12/17~: No night work.
  • 1/4-6: Removal of first contact of ETMY
  • 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
  • 12/21: laser stop in the morning.
  • 12/29,30: line injection.
  • 1/6: End of X arm commissioning.
  • 1/7~ : Opening EXC chamber.
  • 1/7~ : Hight check for VIS systems.
  • 1/17~ : Y arm alignment from BS to ETMY using IR beam.
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
    • 12/18-28: CAL work at EXA