Line 12: Line 12:
 * 12/15, 16 and Week of 12/17~: No night work.  * 12/17~: No night work.
Line 14: Line 14:
 * 1/6: End of X arm commissioning -> Open chambers.  * 1/6: End of X arm commissioning
* end of week of 1/7: Close chambers (ETMX)
Line 16: Line 17:

 * beam alignment:
  * 1/7~: IMC Chambers will open.
   * IMC beam alignment in air: 1/11-14
   * IMC lock recover in vacuum: 1/16
   * IMC to ETMX: 1/17-21
  * BS to ETMY: 1/17-21
  * ITMY to REFL: 1/21-22
  * ITMY to SRM: 1/22-23
  * ITMY to OMC: 1/23-25
  * ITMX to OMC: 1/23-25
  * POS to ETMY(Green laser): 1/23-24
  * ETMY to POS(Green laser): 1/24-25
  * ETMX to ITMX: 2/11-22

 * 2/4~ DRMI Y arm commissioning
Line 17: Line 34:
 * 3/18~ FPMI commissioning

2018/12/17 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance; 12/19: Check RFM for ITMs, changing RT PC etc.
  • 12/17~: No night work.
  • 1/6: End of X arm commissioning
  • end of week of 1/7: Close chambers (ETMX)
  • 1/18~ : Y arm alignment from BS to ETMY using IR beam.
  • beam alignment:
    • 1/7~: IMC Chambers will open.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.