Line 13: Line 13:

 * 1/6: End of X arm commissioning
 * 1/4-6: Removal of first contact of ETMY
 * 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
 * 1/6: End of X arm commissioning.
 * 1/7~ : Opne EXC chamber.
 * 1/7~ : Hight check for VIS systems.
Line 16: Line 19:
 *
Line 18: Line 22:
  * 1/7~: IMC Chambers will open.   * 1/7~: Open IMC Chamber.

2018/12/17 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance; 12/19: Check RFM for ITMs, changing RT PC etc.
  • 12/17~: No night work.
  • 1/4-6: Removal of first contact of ETMY
  • 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
  • 1/6: End of X arm commissioning.
  • 1/7~ : Opne EXC chamber.
  • 1/7~ : Hight check for VIS systems.
  • 1/18~ : Y arm alignment from BS to ETMY using IR beam.
  • beam alignment:
    • 1/7~: Open IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.