2018/12/17 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- Every Wednesday morning: Maintenance; 12/19: Check RFM for ITMs, changing RT PC etc.
- 12/15, 16 and Week of 12/17~: No night work.
1/6: End of X arm commissioning -> Open chambers.
- 1/18~ : Y arm alignment from BS to ETMY using IR beam.
- 2/18~ Y arm commissioning
Discussion
- Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
- X commissioning
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7339: noise investigation for ALS X
- Y arm
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7404: Set up for ALSY system
- VIS
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7348: Drift of the vertical GAS Filter
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7377: PRM, BFLVDT-Glitch
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7389: ETMY, GAS-STM...?
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7395: first version of the inertial damping for the IP of the ITMX
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7406: IP-stage drift and compensation
- Laser, PSL, IOO report
- PCAL
- PEM
- DGS
- Any trouble for updating RCG?