2019/3/11 Commissioning meeting topics
- Assignment of staffs
Schedule
- Center
2/26-27: Venting
- 2/28-3/15: Health check and maintenance for VIS
PRM: One flag was dropped. -> leave it
3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.
- 3/4-8 PRM: Misalignment does not reach where beam hits damper.
~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6
3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.
- 3/18-19: Re-alignment
- 3/19: Closing
- 3/20: pump down
- Yend
1/25-2/20: Yend Pcal finalization
3/5: EYA remaining works by Enomoto, Inoue.
2/25-3/5: Yend WAB finalization
3/6: Y end closing (no laser hazard at least in the morning)
3/7: Y end pump down
3/7,8: leak test
- 3/27: Cooling start
- 4/23: Cooling done
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
2/27: ETMX release
2/23-3/6: Xend Pcal finalization 1
Periscope installation
3/6: Beam position by IR and Green
3/5 AOS: EY and EX(if they have time) work.
3/6: Green X alignment (no IR), and no hazard at Y end.
- 3/11, 18,19: Xend WAB finalization.
- 3/11~3/15: ETMX tuning.
- 3/19: Heatlink etc.
- 3/19: ETMX finalization by Takahashi
- 3/18,19: ETMX alignement
- 3/21 closing
- 3/22 Pumping down
- Leak test
- 4/1: Cooling start
- 4/28: Cooling done
- 3/18~ : Night work starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
2/18-2/22: PRMI commissioning
- 3/25~?: DRMI commissioning
- 3/25-5/?: Y arm commissioning
- 5/?-?/?: FPMI commissioning
Discussion
- Schedule estimation for commissioning.
- Necessary term for each task:
- Y arm lock with green light: 1week
- TF measurement for hierarchy control: 2-4weeks, depending on fluctuation of mass
- Type A payload matrix diagonalize: 2-4weeks, after cooling down
- Y arm lock with mass feedback: 1week
- X arm lock with green light: 1week
- FPMI lock: 1week
- Example1:
- 3/20-3/27: ETMY TF measurement for hierarchy control 1.
- 3/27: ETMY cooling start
- 4/23: ETMY cooling done
- 4/22-5/10: ETMY TF measurement for hierarchy control 2.
- 4/25-5/17: ETMY payload matrix diagonalize
- 5/7-5/10: Y arm lock with green light
- 5/20-5/24 Y arm lock with mass feedback to ETMY
- 4/1: ETMX cooling start
- 4/28: ETMX cooling done
- 4/29-5/10 X arm lock with green light
- 5/27-31: FPMI lock
- when both ends are not available: DRMI lock acquisition. It will be done by 5/31
- 6/3~ DRFPMI lock acquisition
- Example2: Needs ETMI tuning after FPMI commissioning
- 3/25-3/29: Y arm lock with green light
- 4/1: ETMY cooling start
- 4/26: ETMY cooling done
- 3/29: ITMY cooling done
- 4/1-4/26: ITMY TF measurement for hierarchy control 2.
- 4/1-4/26: ITMY payload matrix diagonalize
- 5/7-5/10 Y arm lock with mass feedback to ITMY
- 4/1: ETMX cooling start
- 4/28: ETMX cooling done
- 5/7-5/10 X arm lock with green light
- 5/13-17: FPMI lock
- when both ends are not available: DRMI lock acquisition. It will be done by 5/17
- 5/20~ DRFPMI lock acquisition
- Necessary term for each task:
- Pcal finalization (Inoue)
- Circuit measurement plan (Haino)