2019/3/26 Weekly commissioning meeting topics
- Assignment of staffs
Schedule
- Center
3/25: Venting
- 3/27-4/9: Fixing PR2
4/4 -4/5: Gluing
- 4/8: alignment check
- 4/8-9: OSEM adjustment
- 4/10-11: Closing
- 4/12: Pump down
- 4/15~: Leak check
- ITMX:
3/19: Cooling stop
3/25: Venting start
3/27: Opning chamber
3/27~: Fixing thermal touch
4/2~: closing chamber and start pumping down
- 4/12: Cooling starts.
- Xend
3/25: closing and pump down
- 4/8: Leak check
- 4/9-10: venting
- 4/11: Exchange a broken LED for Photo sensor
- 4/12: closing chamber and start pumping down
- 4/15: Leak check
- 4/19(or 22): Cooling start
- Yend
3/26: Venting start
3/28~: Fixing short inside chamber
4/3: Fixing F0 actuator
4/4~: closing chamber and start pumping down.
- 4/12: Cooling starts.
- 4/8: Daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- April: Measurement of TF, payload diagonalization on ITMX
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Discussion
- Schedule estimation for commissioning with feedback to ITMY.
- 4/12: ETMY cooling start
- 5/9: ETMY cooling done
4/8: ITMY cooling done
- 4/1-4/26: ITMY TF measurement for hierarchy control 2.
- 4/1-4/26: ITMY payload matrix diagonalize
- 5/7-5/17 Y arm lock with mass feedback to ITMY
- 4/12: ITMX cooling start
- 4/19(or 22): ETMX, ITMX cooling start
- 5/9: ITMX cooling done
- 5/16(or 29): ETMX, ITMX cooling done
- 5/13-5/17 X arm lock with green light
- 5/20-24: FPMI lock
- Daily meeting moved to 1pm.
- IOO has night work in week of 4/8.
- Report for ITMY TF measurement.
- Report for ITMY payload matrix diagonalization.
- The minutes of the Type-A kick off meeting is ready:
- Wiki page for the Type-A commissioning: