2019/5/14 Weekly commissioning meeting topics
Zoom URL: https://zoom.us/j/6676627462
- Assignment of staffs
Schedule
- Xend
5/2: Cooling start
- 5/29 cooling will be done.
- 5/12-13: Height adjustment for ITMX and ITMY.
5/14: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS, )
- ~5/17: Y arm lock trial.
- 5/20-24: Exchanging cryo valves.
- ~End of May (might be delayed to middle of June?): Y arm, FPMI commissioning
- Measurement of TF, payload diagonalization on ITMX
Discussion
- Strategy for height difference between ITMX and ITMY.
- Status of Y arm lock trial.
- Feed back to ETMY?