2019/5/14 Weekly commissioning meeting topics
Zoom URL: https://zoom.us/j/6676627462
- Assignment of staffs
Schedule
- 5/20-24: Exchanging cryo valves.
- Center
4/12: Pump down
4/29,30: Leak check
~5/3: Vent and pumpdown
5/9: leak check
- ITMX:
4/2~: closing chamber and start pumping down.
4/10: Cooling starts.
5/8: Cooling done
- Xend
4/25: Pumpdown
5/2: leak check
5/2: Cooling start
- Yend
4/4~: closing chamber and start pumping down.
4/10: Cooling starts.
5/8: Cooling done
- April: Measurement of TF, payload diagonalization on ITMX
- End of April~: Y arm commissioning
- ~End of May (might be delayed to middle of June?): FPMI commissioning
Discussion
- Strategy for height difference between ITMX and ITMY.
- Status of Y arm lock trial.