2019/7/2 11:00-12:00 Weekly commissioning meeting topics
Zoom URL: https://zoom.us/j/6676627462
- Assignment of staffs
Schedule
6/18 Move PR3
- 6/19: DRMI locked.
- 6/21: polarization issue found.
- ITMX
- ETMX
- 6/21: Stop cooler.
- ITMY
- Inject Nitrogen
- 7/2?: pump down again
- ETMY
- 6/20: Stop cooler
- 6/28: Open chamber and fix alignment
- 7/2: Closing chamber and start pump down
- Long term:
4/22-5/31: Yarm commissioning
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Discussion
- Engineering run
- Hours
- IFO configuration
- missing items
Trigger rate during ER slides