Minute of KAGRA commissioning meeting
- Date: 2019/10/5 11:00~12:00
- Attendance: Miyakawa, Oshino, K. Tanaka, Ogaki, Takano, Yamada, Tomura
- Zoom: Miyoki, Uchiyama, Shoda, Sawada, Fujii, Eleonora, Ushiba, Kokeyama, Yokozawa
Discussion
- ASC
- AS/POP WFS is ready.
- REFL will be ready in this week.
- Michelson ASC is with AS WFS
- Single arm ASC with REFL.
- ASC is necessary for TF from global input of BS, ITM, ETM of one of the arm.
- Some time management is necessary for ASC and other work.
- To do list for FPIMI (Yokozawa)
- Michelson measurement was requested by Ogaki.
- It takes 3hours for each MICH, both arms separately, FPMI.
- Noise budget for VIS needs all IFO (Lucia)
- Michelson measurement was requested by Ogaki.
- Propose to have a monitor screen to know VIS status by Miyakawa.
See summary
Others
- Next meeting: 10/15