* Time :''' From 2019/Dec/17(09:00) to 2019/Dec/24(09:00)''' | * Time :''' From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)''' |
Line 5: | Line 5: |
* Rough Schedule || Dec/10-16(09:00) || Commissioning and preparation || || Dec/16(Mon,09:00)~17/(Tue,17:00) || Concentrate longer stable operation of FPMI || || Dec/17(Tue, 17:00) || start || || Dec/24(Tue, 09:00) || end || || Dec/24(Tue, 09:00 ~ (17:00) ) || proposed post ER tasks || ---- === For shifts === * [[KAGRA/EngineeringRun/ER191217_24/Shift|Collaborator shift manuals]] ---- |
|
Line 6: | Line 22: |
* [[ |MIF]] | * [[KAGRA/EngineeringRun/ER191217_24/IFO|IFO(IOO, MIF.LAS)]] |
Line 8: | Line 24: |
* [[ http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_24/PEM|PEM]] | * [[KAGRA/EngineeringRun/ER191217_24/PEM|PEM]] |
Line 11: | Line 27: |
* [[ |DetChar]] * [[ |VIS]] |
* [[KAGRA/EngineeringRun/ER191217_24/DetChar|DetChar]] * [[KAGRA/EngineeringRun/ER191217_24/VIS|VIS]] |
Line 15: | Line 31: |
* [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_23/FCL|FCL]] | * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_24/FCL|FCL]] |
Line 17: | Line 33: |
* [[ |Special for LV ? ]] | * [[KAGRA/EngineeringRun/ER191217_24/forLV |Special for LV and O3]] * [[KAGRA/EngineeringRun/ER191217_24/postERtrial| Post ER trial plans]] |
Line 19: | Line 36: |
* [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_23/Shift|Shift]] |
ER191217~191224
Time : From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)
- Rough Schedule
Dec/10-16(09:00)
Commissioning and preparation
Dec/16(Mon,09:00)~17/(Tue,17:00)
Concentrate longer stable operation of FPMI
Dec/17(Tue, 17:00)
start
Dec/24(Tue, 09:00)
end
Dec/24(Tue, 09:00 ~ (17:00) )
proposed post ER tasks
For shifts
- Subgroup Themes : What will you try and goals for pre-O3 situation.