ER200220~200225
Time : From 2020/Feb/20(17:00) to 2020/Feb/25(09:00)
- Rough Schedule
Feb/20( ~ 11:00)
Commissioning and preparation
Feb/20(11:00)~17:00
Concentrate longer stable operation of RFPMI
Feb/20(17:00)
start
Feb/21
CAL Day (09:00 - 21:00)
Feb/22
Feb/23
Feb/24
Feb/25(09:00)
end
Feb/25(09:00 ~ 13:00 )
Maintenance
Feb/25(17:00 ~ )
Observation
For shifts