- Time and condition
- 9:00 ~ 12:00 or until the end of CAL just before restarting the observation
- The max end time: 16:00
- The blasting for the tunnel construction will not be done from 8:00 to 12:00 every Friday until July 10th (the end day for blasting), according to our negotiation.
Please add your work plat to Teamup
- Contents
(0) 8-9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions.
- Tagoshi-san will inform Miyoki/Ushiba/Sawada, etc. event information around 8 AM. If no events are confirmed, the following (1) can start after we inform Dan-kun.
- (1) 8 or later - 10(roughly):
- CAL for the previous week's observation(CAL-G).
- (2)10-12(roughly): After (1) is finished, we can start (2) in series and in parallel
- Regular TCam photo session just after the morning cal measurement, to monitor the latest mirror center position. It will take ~5 min. (Yuzurihara)
- [Monthly] [1.5 hour] Finesse measurement(Oshino).
- [If necessary] Tidal offload(Ushiba)
- VIS offload if necessary (Takahashi.R)
- Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.)
- Hayakawa-kun or the technical staff will call the control room if the activities are finished.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- (3)13-15:
- Kamioka Mine Company: Tunnel Inspection.(If more IFO/CAL/Detchar, etc., works are necessary, this inspection will be canceled.)
- Hayakawa-kun or the technical staff will call the control room if the activities are finished.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- Kamioka Mine Company: Tunnel Inspection.(If more IFO/CAL/Detchar, etc., works are necessary, this inspection will be canceled.)
- (4)After(3): CAL for the next week's observation.
- (5)Restart observation after(3)
- CAL activities (NEED LINK UPDATE)
Measurement items: JGW-L2314903, Pcal Tcam session
Weekly change in SDF: JGW-L2314962
Expected SDF change duo to Pcal calibration at X/Y end: link
- DGS
- In basic, we don't touch.