KAGRA/Observation/O4c/maintenanceについて、ここに記述してください。 *Time *8:00 ~ 12:00 or until the end of CAL just before restarting the observation |
*Time and condition *9:00 ~ 12:00 or until the end of CAL just before restarting the observation |
Line 6: | Line 4: |
*The blasting for the tunnel construction will not be done from 8:00 to 12:00 every Friday until July 10th (the end day for blasting), according to our negotiation. | |
Line 9: | Line 8: |
*(0)8-9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions. *(1)9-10: CAL for the previous week's observation(CAL-G). The shooting of the mirror height(Yuzurihara). Finesse measurement(Oshino). *(2)10-12(or 12): *Kamioka Mine Company: Tunnel Inspection *Kagra site staff: Instrument checks *VAC/CRY: Checked by Kimura-san + KAGRA site staff |
*(0) 8- 9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions. *(1) 9-11: *CAL for the previous week's observation(CAL-G). *Regular TCam photo session just after the morning cal measurement, to monitor the latest mirror center position. It will take ~5 min. (Yuzurihara) *[Monthly] [1.5 hour] Finesse measurement(Oshino). *(2)11-12: *Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.) *Hayakawa-kun or the technical staff will call the control room if the activities are finished. *VAC/CRY: Checked by Kimura-san + KAGRA site staff. |
Line 16: | Line 18: |
*(3)After(2): CAL for the next week's observation. *(4)Restart observation after(3) |
*(3)13-16: *Kamioka Mine Company: Tunnel Inspection.(If more IFO/CAL/Detchar, etc., works are necessary, this inspection will be canceled.) *Hayakawa-kun or the technical staff will call the control room if the activities are finished. *VAC/CRY: Checked by Kimura-san + KAGRA site staff. *(4)After(3): CAL for the next week's observation. *(5)Restart observation after(3) |
Line 20: | Line 26: |
*Measurement items: [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0149/L2314903/001/CAL_measurement_O4.html|JGW-L2314903]] | *Measurement items: [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0149/L2314903/001/CAL_measurement_O4.html|JGW-L2314903]], [[https://dac.icrr.u-tokyo.ac.jp/KAGRA/DAWG/CAL/O4_CAL_day_week_plan/Pcal_Tcam_session|Pcal Tcam session]] |
*Time and condition
- 9:00 ~ 12:00 or until the end of CAL just before restarting the observation
- The max end time: 16:00
- The blasting for the tunnel construction will not be done from 8:00 to 12:00 every Friday until July 10th (the end day for blasting), according to our negotiation.
- Contents (SHOULD BE DISCUSSED)
(0) 8- 9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions.
- (1) 9-11:
- CAL for the previous week's observation(CAL-G).
- Regular TCam photo session just after the morning cal measurement, to monitor the latest mirror center position. It will take ~5 min. (Yuzurihara)
- [Monthly] [1.5 hour] Finesse measurement(Oshino).
- (2)11-12:
- Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.)
- Hayakawa-kun or the technical staff will call the control room if the activities are finished.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- VIS offload if necessary (Takahashi.R)
- Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.)
- (3)13-16:
- Kamioka Mine Company: Tunnel Inspection.(If more IFO/CAL/Detchar, etc., works are necessary, this inspection will be canceled.)
- Hayakawa-kun or the technical staff will call the control room if the activities are finished.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- Kamioka Mine Company: Tunnel Inspection.(If more IFO/CAL/Detchar, etc., works are necessary, this inspection will be canceled.)
- (4)After(3): CAL for the next week's observation.
- (5)Restart observation after(3)
- CAL activities (NEED LINK UPDATE)
Measurement items: JGW-L2314903, Pcal Tcam session
Weekly change in SDF: JGW-L2314962
- DGS
- In basic, we don't touch.