Line 10: Line 10:
   *Kamioka Mine Company: Tunnel Inspection
Line 14: Line 13:
  *(3)After(2): CAL for the next week's observation.
  *(4)Restart observation after(3)
  *(3)13-14: Kamioka Mine Company: Tunnel Inspection

  *(4
)After(3): CAL for the next week's observation.
  *(5)Restart observation after(3)

*Time

  • 9:00 ~ 12:00 or until the end of CAL just before restarting the observation
  • The max end time: 16:00
  • Contents (SHOULD BE DISCUSSED)
    • (0)8-9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions.

    • (1)9-10: CAL for the previous week's observation(CAL-G). The shooting of the mirror height(Yuzurihara). Finesse measurement(Oshino).
    • (2)10-12:
      • Kagra site staff: Instrument checks
      • VAC/CRY: Checked by Kimura-san + KAGRA site staff
      • VIS offload if necessary (Takahashi.R)
    • (3)13-14: Kamioka Mine Company: Tunnel Inspection
    • (4)After(3): CAL for the next week's observation.
    • (5)Restart observation after(3)
  • CAL activities (NEED LINK UPDATE)
  • DGS
    • In basic, we don't touch.

KAGRA/Observation/O4c/maintenance (last edited 2025-06-13 14:40:38 by shoichi.oshino)