*Time | *Time and condition |
Line 4: | Line 4: |
*The blasting for the tunnel construction will not be done from 8:00 to 12:00 every Friday until July 10th (the end day for blasting), according to our negotiation. |
*Time and condition
- 9:00 ~ 12:00 or until the end of CAL just before restarting the observation
- The max end time: 16:00
- The blasting for the tunnel construction will not be done from 8:00 to 12:00 every Friday until July 10th (the end day for blasting), according to our negotiation.
- Contents (SHOULD BE DISCUSSED)
(0) 8- 9: Confirm NO large SNR events in the last night observing run -> If the events exist, stop the following works and have discussions.
- (1) 9-10: CAL for the previous week's observation(CAL-G). The shooting of the mirror height(Yuzurihara). Finesse measurement(Oshino).
- (2)10-12:
- Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.)
- Hayakawa-kun or the technical staff will call the control room if the activities are finished.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- VIS offload if necessary (Takahashi.R)
- Kagra site staff: Instrument checks (Please call Hayakawa-kun to allow the activities in the KAGRA site. If during his absence, please call Takahashi(masa)-san, or Sawada-san or Yamaguchi-san, in this order.)
- (3)13-14: Kamioka Mine Company: Tunnel Inspection.
- VAC/CRY: Checked by Kimura-san + KAGRA site staff.
- (4)After(3): CAL for the next week's observation.
- (5)Restart observation after(3)
- CAL activities (NEED LINK UPDATE)
Measurement items: JGW-L2314903
Weekly change in SDF: JGW-L2314962
- DGS
- In basic, we don't touch.