Line 5: Line 5:
  * Recovery just after disasters:
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28212,

  * Cable cut and repair
   * Recovery of BF damper: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28640
   * treatment: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29003
Line 6: Line 13:
   *    * Photosensor:
    * Investigation and recovery: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28765
    * Repair: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28811
    * Glitches: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28430, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29753, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29816

   * Cable replacement
    * ETMY MN LEN OpLev is very noisy: https://klog.icrr.u-tokyo.ac.jp/osl/?r=27776

   * Resistance/Inductance
    * BF LVDT: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28550
    * F2 LVDT: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29780
    * F2 GAS signal: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29603, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29622
    * LVDT coils for BF damper: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29199
Line 9: Line 29:
Line 10: Line 31:
   *    * Investigation of BF horizontal actuator: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29451
Line 13: Line 35:
Line 14: Line 37:
Line 15: Line 39:
   *    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29083
Line 17: Line 42:
Line 18: Line 44:
   *    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28430
   * ETMY F2 GAS signals got strange in this morning: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29603
Line 20: Line 48:
   *    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28430

  * A11: EQ stopper
   * check:https://klog.icrr.u-tokyo.ac.jp/osl/?r=29604

  *(A12: Inertial Damping)
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29715, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29750
Line 22: Line 57:
  *   * Just after disasters: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28216, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28221, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28246, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28252
  * Check before closing: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29206
Line 24: Line 61:
  *
 * X-Pcal homeworks
  *
  * Path finder: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28861
  * Flash finder:https://klog.icrr.u-tokyo.ac.jp/osl/?r=29115
  * Flash check again before closing.

 * Y-Pcal homework
  * Healthy just after disasters: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28210
  * Oil pollution !!
  * Recovery including mirror cleaning: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29738
  * Review document: https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=15844
Line 29: Line 72:
  * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28730
Line 32: Line 76:
  *   * just after disaster: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28410
  * maintenance: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28642, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28644
  * Cleaning: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29213, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29901
  * Reclaening ??
  * Image Analysis: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29330
Line 34: Line 82:
 * TMSX optical system (Akutsu and his selected persons)  * TMSY optical system (Akutsu and his selected persons)
Line 37: Line 85:
  *   * not necessary.
Line 40: Line 88:
  *   * NAB@EYA
   * Mechanically healthy: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28997
   * Concerns: pollution with oil -> Noway to clean it, except for the suspension base-frame that was cleaned.
  *WAB@EYC
   * Mechanically healthy: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28620
   * EY WAB restained and released: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28620, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28871
Line 43: Line 97:
  * tie rod adjustment between EXC and TMSX to avoid stress when the only EXC side is pumped down.
  * Nasty air parts were replaced.
  * Vacuum alert recovery after pumping down.
  * tie rod adjustment between EYC and TMSY to avoid stress when the only EYC side is pumped down.
  * Nasty air parts were replaced. -. Done
  * Vacuum alert recovery after pumping down. 
Line 47: Line 101:
  * The broken cc-10 was replaced.
  * N2 purge is necessary for EXV.
  * Pumping down from EYA


EYC Recovery(20240407)


KAGRA/Recovery2024/EYC (last edited 2024-07-03 06:30:23 by miyoki)