Line 105: Line 105:
Oplev Check for IMMT1. (Yokozawa-kun) Oplev Check for PRM, IMMT1. (Yokozawa-kun)


Suspension Condition of PRM, IMMT1/2. (Takahashi-san, Ushiba-kun)


IMMT1/2, PRM

  • Mirror conditions(??)
    • Clean around the center?


Beam Path from IMC to PRM (Yokozawa-kun, and Akutsu-kun)


Activities:

IMC to STM1

  • Beam clearance: OK

STM1/2

  • Mirror mount stability with cables
  • Beam positions on them
  • Trans beam from STM2

IFI to IMMT1

  • IFI injection: No clipping
  • Beam position on IMMT1
  • Trans beam of IMMT1
    • No change to ISS path?
    • ISS beam/CWP reflection beam extracting (??)
    • the beam paths are clear?
    • The beams hit around the center of windows?
    • The reflected beams on the windows are dumped?

IMMT1-IMMT2

  • Beam clearance: no problem
  • Beam position on IMMT2: shifted from the center.

IMMT2-PRM

  • Main beam/misaligned beam clearances: no problem against the beam dumper
  • The misaligned beam position: hits on the dumper(?) and the temp enhancement was detected.

Around PRM

  • Beam position on PRM
  • IR beam in the midsize baffles(HR/AR side)

Main Beam Dumper

Beam dump(T.Akutsu)


PRM Cleaning (Hirata-san, Aso-kun)


PRM


Oplev Check for PRM, IMMT1. (Yokozawa-kun)


Activities:

Beam Power

Beam Path Clearance

  • IMMT1

QPD centering

Calibration

Spectrum Health

Oplev beam's stray light influence

  • almost no light? as before.

Oplev table covering

  • we will do this after closing.


ISS path


Check the path by Miyakawa-kun

  • ??


Vacuum system (Kimura/Uchiyama and their selected persons)


Close GV btw PRM and PR3 and stad bolt nut adjustment btw PRM and PR3

Clean inside as much as possible including the bellows duct with TMP

Check the flange seal surface condition where were opened.

Decide where the elastomer/Metal gasket will be used.

Logistic to reinstall the bellows duct with TMP.

  • Sawada-sana and Mirapro members call
  • If you use chain block, please be careful of its fixing