IXC Recovery(20240407)
- Suspension health check (Takahashi, Ushiba)
- A01: Cable check
- A02 Porality Check
- A03 Rubbing Check
- A04: Range and Calibration
- A05: Watchdog Setting: Skip
- A06: Height Measurement
A08: Calibration:skip
- A09: Spectrum
- A10: Transfer Function
- A01: Cable check
- Oplev Check (Yokozawa, Akutsu)
- Green flash at REFL and Trans PD
- X-Pcal homeworks
- Windows Cleaning
Tcam (Yokozawa and ChenDan, and Yamamoto)
- TMSX optical system (Akutsu and his selected persons)
- Baffle PDs (Yokozawa and his selected persons):
- NAB, WAB (Akutsu)
- Vacuum system (Kimura-san / Uchiyama-kun and their selected persons)
- tie rod adjustment between EXC and TMSX to avoid stress when the only EXC side is pumped down.
- Nasty air parts were replaced.
- Vacuum alert recovery after pumping down.
- GV interlock will be tried after pumping down.
- The broken cc-10 was replaced.
- N2 purge is necessary for EXV.
- Cryo-system (Kimura-san and his selected persons)
- All temp signals are obtained?
- Connector change is required for the heat link suspensions.
- Cryocon alert to slack after cooling.
- No interlock for TMP around the Cryostat.