Revision 5 as of 2024-04-09 09:46:41
Size: 1891
Editor: miyoki
Comment:
Revision 9 as of 2024-04-09 14:27:16
Size: 1621
Editor: miyoki
Comment:
Deletions are marked like this. Additions are marked like this.
Line 24: Line 24:
 * Green flash at REFL and Trans PD
  *
 * X-Pcal homeworks
  *
Line 43: Line 39:
  * tie rod adjustment between EXC and TMSX to avoid stress when the only EXC side is pumped down.
Line 47: Line 42:
  * The broken cc-10 was replaced.
* N2 purge is necessary for EXV.
  * N2 purge is necessary for IXV.
Line 52: Line 46:
  * Connector change is required for the heat link suspensions.


IXC Recovery(20240407)