Differences between revisions 1 and 32 (spanning 31 versions)
Revision 1 as of 2024-05-29 05:59:26
Size: 1205
Editor: miyoki
Comment:
Revision 32 as of 2024-05-31 17:12:28
Size: 7512
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
PR2,3,BS,SRM,SR2,SR3 Cleaning PR2,3,BS,SRM,SR2,SR3 Cleaning(Aso-kun, Hirata-san)
Line 4: Line 4:
PR2 PR2: Acceptable after FCing
 * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29228
Line 6: Line 7:
PR3 PR3: Slight dots could not be removed by even pure water. We accepted this situation.
 * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29520
Line 9: Line 11:
 * Did you eyeballs checks during the beam path check?
Line 12: Line 15:
Suspension Health check PR2,3, BS, SRM, SR2, SR3. (Takahashi-san, Ushiba-kun) Suspension Condition of PR2, PR3, BS, SR3, SR2, SRM. (Takahashi-san, Ushiba-kun, Hirata-san)
Line 14: Line 17:
  * Mechanical Motion
   * Smooth pico motion and its default position: skip
   * Gaps between magnets and coils :skip
   * Gaps between EQ stoppers and mirrors
    * PR2: OK
      * (Recovery Work)https://klog.icrr.u-tokyo.ac.jp/osl/?r=28593
      * Position measurement of the traverse: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28637, 3mm +Y side adjustment was done.
    * PR3: OK
     * (Recovery Work)https://klog.icrr.u-tokyo.ac.jp/osl/?r=28509
     * Position measurement of the traverse: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28718
    * BS : OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29682
    * SRM: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29594
    * SR2: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29595
    * SR3: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29596
    * SRMs: OK for wider space: total comments: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29612
Line 15: Line 33:
  * IP adjustment
   * BS: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28359
   * SR2 : https://klog.icrr.u-tokyo.ac.jp/osl/?r=28355
   * SR3: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28353
   * SRM: OK even after earthquakes.
   * Temperature should be the same in the future.
      
  * Electrical wirings
   * Coil resistances and inductances ->
    * PR2: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29429
    * PR3: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29430
    * BS : OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29088, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29014
    * SRM:
    * SR2:
    * SR3:
Line 16: Line 49:
  * DAC noise
   * SRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=26230
   * SR2/3: done before Jan 1st 2024.
Line 17: Line 53:
  * OSEM conditions: Ratations were found so much. But they could be acceptable from the point t of view of signals.
   * RP2: OK: (Recovery Work)https://klog.icrr.u-tokyo.ac.jp/osl/?r=28593
   * RP3: OK: (Recovery Work)https://klog.icrr.u-tokyo.ac.jp/osl/?r=28509
   * BS : OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29156, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29379
   * SRM: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29317, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29323, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29594
   * SR2: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29315, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29322, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29595
   * SR3: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29316, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29321, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29596
Line 18: Line 61:
  * Smooth Mag-coil motion and balance and TFs
  * Spectrum ---> Should be taken.
   * PR2: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28674, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28768, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28770, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28774,
   * PR3: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28808, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29648,
   * BS: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28292, https://klog.icrr.u-tokyo.ac.jp/osl/?r=28352, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29432
   * SRM: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28373, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29584
   * SR2: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28369, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29498
   * SR3: OK: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28368, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29199 (TF is OK, Blending problem happened on the peaks. Please write this contents in klog!)
Line 24: Line 74:
Activities:
Activities
 * All seem to be fine: BS, SR2, SR3, SRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29670
 * Photos in PR2 and PR3 chambers will be taken.
Line 31: Line 82:
 *  *beam pathes were checked but it is difficult to take photos.
  *PR2: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29345
  *PR3: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28896
  *BS and SRs: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29670
Line 51: Line 105:
Beam path and Baffle Position Beam Path and Baffle Position
Line 53: Line 107:
 *   * IR
   * Optical beam alignment from BS to SRM
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29635
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29630
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29632
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29635
   * Mid baffles and stray light inspection around SR3, SR2, and SRM
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29629
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29636
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29642
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29690
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29703
   * SR transmission (IR) will be checked.
   * SRM front surface reflection could not be found.
   * IR beam might be clipped at PR3 HR mid-baffle.
Line 55: Line 123:
  *GR
   * GRX
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28558
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28579
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28860
    * TMSX : https://klog.icrr.u-tokyo.ac.jp/osl/?r=29131
    * for IFI-PRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29261
    * for IFI-PRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29282
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29299
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29341

   * GRY
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28689
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28827
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28847
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28861
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28898
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28920
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29115

 * IR/GR arm alignment
  * X-arm:
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29346,
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29448,
   * Finesse: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29586
  * Y-arm: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29478
Line 59: Line 153:
 *  * Finished: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29146, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29088, https://klog.icrr.u-tokyo.ac.jp/osl/?r=29146
Line 65: Line 159:
Open the GV between SRM-SR3, and Close the GV between SRM-OMC !!
 * tierod adjustment for the GV on the SRM side.
Line 67: Line 163:
 * maybe impossible from the only side hatches.  * PR3, PR3, BS :
 * SR2, SR3, SRM :
maybe impossible from the only side hatches.
Line 77: Line 174:
 *  * PR2: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29413
 * PR3: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29412
Line 83: Line 181:
 *


PR2,3,BS,SRM,SR2,SR3 Cleaning(Aso-kun, Hirata-san)


PR2: Acceptable after FCing

PR3: Slight dots could not be removed by even pure water. We accepted this situation.

No cleaning for BS, SRM, SR2, SR3

  • Did you eyeballs checks during the beam path check?


Suspension Condition of PR2, PR3, BS, SR3, SR2, SRM. (Takahashi-san, Ushiba-kun, Hirata-san)



Oplev Check for PR2,3,BS,SRM,SR2,SR3. (Yokozawa-kun)


Activities

Beam Power

Beam Path Clearance

QPD centering

Calibration

Spectrum Health

Oplev beam's stray light influence

  • almost no light?

Oplev table covering

  • we will do this after closing.


Beam Path and Baffle Position



Leaked hermetic flange repair on BS



Vacuum system (Kimura/Uchiyama and their selected persons)


Open the GV between SRM-SR3, and Close the GV between SRM-OMC !!

  • tierod adjustment for the GV on the SRM side.

Clean inside as much as possible including the bellows duct with TMP

  • PR3, PR3, BS :
  • SR2, SR3, SRM : maybe impossible from the only side hatches.

Check the flange seal surface condition where were opened.

Decide where the elastomer/Metal gasket will be used.

Check the opened flanges and the top hut of PRM2, 3

Logistic to reinstall the bellows duct with TMP.

  • Sawada-sana and Mirapro members call
  • If you use chain block, please be careful of its fixing
  • Careful cramp tightening near oplevs.

KAGRA/Recovery2024/MICH (last edited 2024-05-31 17:12:28 by takafumi.ushiba)