Line 27: Line 27:
    * BS     * BS : https://klog.icrr.u-tokyo.ac.jp/osl/?r=29682
Line 73: Line 73:
 * BS, SR2, SR3, SRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29670  * All seem to be fine: BS, SR2, SR3, SRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29670
Line 113: Line 113:
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28558
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28579
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28860
    * TMSX : https://klog.icrr.u-tokyo.ac.jp/osl/?r=29131
    * for IFI-PRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29261
    * for IFI-PRM: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29282
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29299
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29341
Line 114: Line 123:
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28689
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28827
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28847
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28861
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28898
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28920
    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29115

 * IR/GR arm alignment
  * X-arm:
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29346,
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29448,
   * Finesse: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29586
  * Y-arm: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29478


PR2,3,BS,SRM,SR2,SR3 Cleaning


PR2

PR3

No cleaning for BS, SRM, SR2, SR3

  • Did you eyeballs check during the beam path check?


Suspension Condition of PR2, PR3, BS, SR3, SR2, SRM. (Takahashi-san, Ushiba-kun, Hirata-san)


  • Mirror conditions(??)
    • Clean around the center?


Oplev Check for PR2,3,BS,SRM,SR2,SR3. (Yokozawa-kun)


Activities

Beam Power

Beam Path Clearance

QPD centering

Calibration

Spectrum Health

Oplev beam's stray light influence

  • almost no light?

Oplev table covering

  • we will do this after closing.


Beam Path and Baffle Position



Leaked hermetic flange repair on BS



Vacuum system (Kimura/Uchiyama and their selected persons)


Clean inside as much as possible including the bellows duct with TMP

  • maybe impossible from the only side hatches.

Check the flange seal surface condition where were opened.

Decide where the elastomer/Metal gasket will be used.

Check the opened flanges and the top hut of PRM2, 3

Logistic to reinstall the bellows duct with TMP.

  • Sawada-sana and Mirapro members call
  • If you use chain block, please be careful of its fixing
  • Careful cramp tightening near oplevs.

KAGRA/Recovery2024/MICH (last edited 2024-05-31 17:12:28 by takafumi.ushiba)