20180918

  • [[]]

Today's activities

Workers: Akutsu, Uraguchi, Yano at Mitaka

  • Passed the TMS-VIS, the BRT, and some parts including geophones to the transportation comapny.

Next plan

  • Accpet those above.
  • Bring them to the Xend.
  • Wait until one day so that the temperature of them will become equilibrium with the environment in the Xend.