Line 12: Line 12:
 * Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.)
Line 14: Line 15:
 *  * First contact to clean the side diameter of the optics.

20180918

  • [[]]

Today's activities

Workers: Akutsu, Uraguchi, Yano at Mitaka

  • Passed the TMS-VIS, the BRT, and some parts including geophones to the transportation comapny.

Next plan

  • Accpet those above.
  • Bring them to the Xend.
  • Wait until one day so that the temperature of them will become equilibrium with the environment in the Xend.
  • Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.)

Wanted!

  • First contact to clean the side diameter of the optics.

KAGRA/Subgroups/AOS/TMSX_O3/2018-09-18 (last edited 2018-09-18 23:38:46 by TomotadaAkutsu)