2019/09/04
18:00 JST (Japan) 17:00 CST (Taiwan) 10:00 CET (Geneva)
- Yuki and Task manager: Schedule
Yuki: Line study klog
- Pang: Result of Pcal stabirity
- Wu-Cheng: Current status of the offline server
Memo LVC meeting: On going
- Online
- Software part is almost done.
- Kappa monitoring: Not urgent.
- Low Latency
- Provide h(t). Inverse AAAI. not include time dependency part.
- Offline
- calgst-hl
- FSM
- Started the measurement.
- Slide: JPS meeting.
- DARM
- Pcal
- Disconnect WF at X-end (9/6 afternoon, Yamamoto-san, Ogaki-kun, Thanks!)
- Line injection will start next week 15.8Hz (9/9-)
- After that, we will inject the software and actuator lines at 15.9Hz, 15.7Hz
- We will fix the Y-end system on middle Sep.
- Gcal