Differences between revisions 7 and 8
Revision 7 as of 2018-06-21 17:39:50
Size: 4427
Comment:
Revision 8 as of 2018-06-21 17:41:48
Size: 4431
Comment:
Deletions are marked like this. Additions are marked like this.
Line 19: Line 19:
Line 25: Line 26:
     * '''As a prerequisite to this task, DT reproduced a portion of LIGO h(t) from raw data with gstlal-calibration-v1.1.8 (w/ a "docker-gstlal-cold" image).      * '''As a prerequisite to this task, DT reproduced a portion of LIGO h(t) from raw data with gstlal-calibration-v1.1.8 (w/ a "docker-gstlal-cold" image).'''
Line 27: Line 28:
     This test was done on a private server (2-cores on Intel Xeon 2.4GHz, 8GB RAM).'''
This test was done on a private server (2-cores on Intel Xeon 2.4GHz, 8GB RAM).

Low-latency and offline

Current tasks (May 26 - July 15):

  • Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ongoing | expected finish: N/A]

  • Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ongoing | expected finish: Jul 15]

    • Find names and versions of all prerequisite libraries
    • Install prerequisites and gstlal-cal package on a machine at AS
    • Test gstlal-cal pipeline on an AS machine
    • Install prerequisites and gstlal-cal package on a machine at KAGRA
    • Test the pipeline on a KAGRA machine

Progress so far (June 21):

  • Ask LIGO CAL team for the detailed information of gstlal-calibration
    • (ongoing) gstlal-calibration maintainers in LIGO are helping to resolve some installation and testing issues.

  • Find names and versions of all prerequisite libraries,
  • Install required packages and the gstlal-cal package on a machine at AS
  • Test gstlal-cal pipeline on an AS machine
    • As a prerequisite to this task, DT reproduced a portion of LIGO h(t) from raw data with gstlal-calibration-v1.1.8 (w/ a "docker-gstlal-cold" image). This test was done on a private server (2-cores on Intel Xeon 2.4GHz, 8GB RAM).

    • Downloaded a few hours of bKAGRA Phase-1 data on AS machine.

    • (doing) Will try to reproduce C00 with gstlal-calibration. Details in

    • (to do) Verify the output of gstlal-calibration.

  • Install prerequisites and gstlal-cal package on a machine at KAGRA
  • Test the pipeline on a KAGRA machine gstlal tests

    • to do

  • Documentation

Progress so far (June 7):

  • Ask LIGO CAL team for the detailed information of gstlal-calibration
    • Communication with people working on LIGO gstlal has been initiated.

  • Find names and versions of all prerequisite libraries,
  • Install prerequisites and gstlal-cal package on a machine at AS
    • As a prerequisite to this task, SH worked on installation process for CentOS, DT for Debian.

    • The goal is to have a better understanding of what is happening under the hood when the gstlal-calibration package is compiled.

  • Test gstlal-cal pipeline on an AS machine
    • As a prerequisite to this task, DT is currently trying to reproduce LIGO h(t) from raw data.

    • A sub-goal of this task is to come up with a gstlal code testing procedure.

    • DT addressed some questions to LIGO gstlal people.

  • Install prerequisites and gstlal-cal package on a machine at KAGRA
  • Test the pipeline on a KAGRA machine gstlal tests

    • to do

New tasks:

  • Put more effort on documentation.

KAGRA/Subgroups/CAL/Low-latency_and_offline (last edited 2020-07-25 03:17:08 by darkhan.tuyenbayev)