Shift
Task list
Kamioka shift
- connectiong of EYA PC to CDS (2days)
- connectiong of EXA PC to CDS (2days)
- connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo)
- connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo)
- IXA camera install(1 week)(IXA camera is not related cal work? T.Yo)
- Preparing the CAL-Git server (2days)
- EX Pcal shipping(1week)
- EXA AA/AI install (1day)
- EYA de-whitening install (1day)
- EXA Cabling (3days)
- EXA Tx alignment(3days)
- EXA Periscope alignment(3days)
- EXA Rx alignment(1days)
- Replacing the 2inch lenses on EYA (2days)(??? T.Yo)
- NAB EXA (1 week)(may change to 2-3day. T.Yo)
- NAB EYA (1 week)(may change to 2-3day. T.Yo)
- NAB IYA (1 week)(IYA issue is not related cal work? T.Yo)
- WSK calibration(Every month)
- Camera tuning EYA (2days)
- Camera tuning EXA (2days)
- Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo)
- Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo)
KEK
Member:(Tomaru), Kozakai,Bin-Hua
OCU
Member: (Kanda),Sawada,Tsuchida
ICRR
Member: Yamamoto,Yokozawa
NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) (IXA work is not related to CAL tasks)
Taiwan
Academia Sinica
Member: (Haino), Cory, Darkhan
NCU
Member: Inoue, Bill, Pang