== KEK == -Takayuki Tomaru -Chihiro Kozakai |
= Shift = |
Line 5: | Line 3: |
== ICRR == -Takaaki Yokozawa -Takahiro Yamamoto |
|
Line 9: | Line 4: |
== OCU == -Nobuyuki Kanda - - |
== Task list == |
Line 14: | Line 6: |
== ASIoP == -Sadakazu Haino -Yuki Inoue -Darkhan Tuyenbayev |
=== Kamioka shift === * connectiong of EYA PC to CDS (2days) * connectiong of EXA PC to CDS (2days) * connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo) * connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo) * IXA camera install(1 week)(IXA camera is not related cal work? T.Yo) * Preparing the CAL-Git server (2days) * EX Pcal shipping(1week) * EXA AA/AI install (1day) * EYA de-whitening install (1day) * EXA Cabling (3days) * EXA Tx alignment(3days) * EXA Periscope alignment(3days) * EXA Rx alignment(1days) * Replacing the 2inch lenses on EYA (2days)(??? T.Yo) * NAB EXA (1 week)(may change to 2-3day. T.Yo) * NAB EYA (1 week)(may change to 2-3day. T.Yo) * NAB IYA (1 week)(IYA issue is not related cal work? T.Yo) * WSK calibration(Every month) * Camera tuning EYA (2days) * Camera tuning EXA (2days) * Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo) * Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo) === KEK === Member:(Tomaru), Kozakai,Bin-Hua === OCU === Member: (Kanda),Sawada,Tsuchida === ICRR === Mamber: Yamamoto,Yokozawa * --( NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) )-- (IXA work is not related to CAL tasks) === Taiwan === ==== Academia Sinica ==== Member: (Haino), Cory, Darkhan ==== NCU ==== Member: Inoue, Bill * Alignment of Y-end Pcal with vaccuming (2days) -> Yuki, (+Kimura-san):Not yet (2018/6/14-15) |
Shift
Task list
Kamioka shift
- connectiong of EYA PC to CDS (2days)
- connectiong of EXA PC to CDS (2days)
- connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo)
- connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo)
- IXA camera install(1 week)(IXA camera is not related cal work? T.Yo)
- Preparing the CAL-Git server (2days)
- EX Pcal shipping(1week)
- EXA AA/AI install (1day)
- EYA de-whitening install (1day)
- EXA Cabling (3days)
- EXA Tx alignment(3days)
- EXA Periscope alignment(3days)
- EXA Rx alignment(1days)
- Replacing the 2inch lenses on EYA (2days)(??? T.Yo)
- NAB EXA (1 week)(may change to 2-3day. T.Yo)
- NAB EYA (1 week)(may change to 2-3day. T.Yo)
- NAB IYA (1 week)(IYA issue is not related cal work? T.Yo)
- WSK calibration(Every month)
- Camera tuning EYA (2days)
- Camera tuning EXA (2days)
- Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo)
- Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo)
KEK
Member:(Tomaru), Kozakai,Bin-Hua
OCU
Member: (Kanda),Sawada,Tsuchida
ICRR
Mamber: Yamamoto,Yokozawa
NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) (IXA work is not related to CAL tasks)
Taiwan
Academia Sinica
Member: (Haino), Cory, Darkhan
NCU
Member: Inoue, Bill
Alignment of Y-end Pcal with vaccuming (2days) -> Yuki, (+Kimura-san):Not yet (2018/6/14-15)