=== Kamioka shift === |
|
Line 6: | Line 10: |
* connectiong of IYA PC to CDS (2days) * connectiong of IXA PC to CDS (2days) * IXA camera install(1 week) |
* connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo) * connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo) * IXA camera install(1 week)(IXA camera is not related cal work? T.Yo) |
Line 10: | Line 14: |
* EX Pcal shipping(1week) | |
Line 16: | Line 21: |
* Replacing the 2inch lenses on EYA (2days) * NAB EXA (1 week) * NAB EYA (1 week) * NAB IYA (1 week) |
* Replacing the 2inch lenses on EYA (2days)(??? T.Yo) * NAB EXA (1 week)(may change to 2-3day. T.Yo) * NAB EYA (1 week)(may change to 2-3day. T.Yo) * NAB IYA (1 week)(IYA issue is not related cal work? T.Yo) |
Line 21: | Line 26: |
* Camera tuning EYA (2days) * Camera tuning EXA (2days) * Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo) * Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo) |
|
Line 23: | Line 32: |
Member:(Tomaru), Kozakai,Bin-Hua | |
Line 25: | Line 35: |
Member: (Kanda),Sawada,Tsuchida | |
Line 27: | Line 38: |
* NAB IXA (1 week)->Yokozawa: On going | Mamber: Yamamoto,Yokozawa * --( NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) )-- (IXA work is not related to CAL tasks) |
Line 31: | Line 43: |
Member: (Haino), Cory, Darkhan | |
Line 33: | Line 46: |
Member: Inoue, Bill, Pang |
Shift
Task list
Kamioka shift
- connectiong of EYA PC to CDS (2days)
- connectiong of EXA PC to CDS (2days)
- connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo)
- connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo)
- IXA camera install(1 week)(IXA camera is not related cal work? T.Yo)
- Preparing the CAL-Git server (2days)
- EX Pcal shipping(1week)
- EXA AA/AI install (1day)
- EYA de-whitening install (1day)
- EXA Cabling (3days)
- EXA Tx alignment(3days)
- EXA Periscope alignment(3days)
- EXA Rx alignment(1days)
- Replacing the 2inch lenses on EYA (2days)(??? T.Yo)
- NAB EXA (1 week)(may change to 2-3day. T.Yo)
- NAB EYA (1 week)(may change to 2-3day. T.Yo)
- NAB IYA (1 week)(IYA issue is not related cal work? T.Yo)
- WSK calibration(Every month)
- Camera tuning EYA (2days)
- Camera tuning EXA (2days)
- Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo)
- Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo)
KEK
Member:(Tomaru), Kozakai,Bin-Hua
OCU
Member: (Kanda),Sawada,Tsuchida
ICRR
Mamber: Yamamoto,Yokozawa
NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) (IXA work is not related to CAL tasks)
Taiwan
Academia Sinica
Member: (Haino), Cory, Darkhan
NCU
Member: Inoue, Bill, Pang