Shift
Task list
- connectiong of EYA PC to CDS (2days)
- connectiong of EXA PC to CDS (2days)
- connectiong of IYA PC to CDS (2days)
- connectiong of IXA PC to CDS (2days)
- IXA camera install(1 week)
- Preparing the CAL-Git server (2days)
- EXA AA/AI install (1day)
- EYA de-whitening install (1day)
- EXA Cabling (3days)
- EXA Tx alignment(3days)
- EXA Periscope alignment(3days)
- EXA Rx alignment(1days)
- Replacing the 2inch lenses on EYA (2days)
- NAB EXA (1 week)
- NAB EYA (1 week)
- NAB IYA (1 week)
- WSK calibration(Every month)
KEK
OCU
ICRR
NAB IXA (1 week)->Takaaki: On going (2018/6/11-15)
Taiwan
Academia Sinica
NCU
Alignment of Y-end Pcal with vaccuming (2days) -> Yuki (2018/6/14-15)