=== Kamioka shift ===
Line 7: Line 9:
 * connectiong of IYA PC to CDS (2days)
 * connectiong of IXA PC to CDS (2days)
 * IXA camera install(1 week)
 * connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo)
 * connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo)
 * IXA camera install(1 week)(IXA camera is not related cal work? T.Yo)
Line 11: Line 13:
 * EX Pcal shipping(1week)
Line 17: Line 20:
 * Replacing the 2inch lenses on EYA (2days)
 * NAB EXA (1 week)
 * NAB EYA (1 week)
 * NAB IYA (1 week)
 * Replacing the 2inch lenses on EYA (2days)(??? T.Yo)
 * NAB EXA (1 week)(may change to 2-3day. T.Yo)
 * NAB EYA (1 week)(may change to 2-3day. T.Yo)
 * NAB IYA (1 week)(IYA issue is not related cal work? T.Yo)
Line 24: Line 27:
 * Camera tuning IYA (2days)
 * Camera tuning IXA (2days)
 * Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo)
 * Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo)
 * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8405
Line 28: Line 32:
Member:(Tomaru), Kozakai,Bin-Hua
Line 30: Line 35:
Member: (Kanda),Sawada,Tsuchida
Line 32: Line 38:
 * NAB IXA (1 week)->Takaaki: On going (2018/6/11-15) Mamber: Yamamoto,Yokozawa
* --( NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) )-- (IXA work is not related to CAL tasks)
Line 36: Line 43:
Member: (Haino), Cory, Darkhan
Line 38: Line 46:
 * Alignment of Y-end Pcal with vaccuming (2days) -> Yuki, (+Kimura-san) (2018/6/14-15) Member: Inoue, Bill
 

Shift

Task list

Kamioka shift

  • connectiong of EYA PC to CDS (2days)
  • connectiong of EXA PC to CDS (2days)
  • connectiong of IYA PC to CDS (2days)(IYA camera is not related cal work? T.Yo)
  • connectiong of IXA PC to CDS (2days)(IXA camera is not related cal work? T.Yo)
  • IXA camera install(1 week)(IXA camera is not related cal work? T.Yo)
  • Preparing the CAL-Git server (2days)
  • EX Pcal shipping(1week)
  • EXA AA/AI install (1day)
  • EYA de-whitening install (1day)
  • EXA Cabling (3days)
  • EXA Tx alignment(3days)
  • EXA Periscope alignment(3days)
  • EXA Rx alignment(1days)
  • Replacing the 2inch lenses on EYA (2days)(??? T.Yo)
  • NAB EXA (1 week)(may change to 2-3day. T.Yo)
  • NAB EYA (1 week)(may change to 2-3day. T.Yo)
  • NAB IYA (1 week)(IYA issue is not related cal work? T.Yo)
  • WSK calibration(Every month)
  • Camera tuning EYA (2days)
  • Camera tuning EXA (2days)
  • Camera tuning IYA (2days)(IYA camera is not related cal work? T.Yo)
  • Camera tuning IXA (2days)(IXA camera is not related cal work? T.Yo)
  • https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8405

KEK

Member:(Tomaru), Kozakai,Bin-Hua

OCU

Member: (Kanda),Sawada,Tsuchida

ICRR

Mamber: Yamamoto,Yokozawa

  • NAB IXA (1 week)->Takaaki (+Akutsu-san): On going (2018/6/11-15) (IXA work is not related to CAL tasks)

Taiwan

Academia Sinica

Member: (Haino), Cory, Darkhan

NCU

Member: Inoue, Bill