Line 18: | Line 18: |
* List-up tasks and responsible person(s) * List-up milestones and deadline * Submit the list of task and milestone to the KAGRA scheduler |
* --(List-up tasks and responsible person)-- * --(List-up milestones and deadline)-- * --(Submit the list of task and milestone to the KAGRA scheduler)-- |
Line 22: | Line 22: |
=== Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua) === * Install Pcal at X and Y-end and coordinate the long-term Pcal characterization |
=== Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua,c.Bill) === [[PcalTask]] * Install Pcal at X and Y-end and coordinate[status: ''on going'' | expected finish: '''Sep. 1, 2018'''] * the long-term Pcal characterization [status: ''to do'' | expected finish: '''Sep. 1, 2018'''] |
Line 25: | Line 27: |
* List-up the systematic error budget table for O3 * Achieve 1% displacement error * Contact person of working standard of Toyama univ. * Absolute calibration organization * Maintenance at Kamioka site. * BH should stay Kamioka and periodic work |
* List-up the systematic error budget table for O3 [status: ''on going'' | expected finish: '''until O3'''] * Achieve 1% displacement error [status: ''to do'' | expected finish: '''Apr. 1, 2019'''] * Absolute power calibration[status: ''to do'' | expected finish: '''Jan. 1, 2019'''] *Note: Maintenance at Kamioka site. * BH should stay Kamioka and periodic work * Telephoto camera * Installation is almost done * Maintenance of TCam is done by T.Yokozawa * IR filter issue(spare camera), additional spare camera. * Image analysis by Tomigami. |
Line 32: | Line 38: |
=== Front-end (T.Yamamoto, +1person from off-site) === * Make the models for the online h(t) reconstruction * Provide the necessary DAQ channels for the low-latency calibration |
=== Front-end (T.Yamamoto, T.Sawada) === * Make the models for the online h(t) reconstruction [status: ''ongoing'' | expected finish: '''Jan. 1, 2019'''] * Provide the necessary DAQ channels for the low-latency calibration[status: ''ongoing'' | expected finish: '''Jan. 1, 2019'''] * The necessary channels had already existed in Phase-1 operation (What we should are only small fix.). |
Line 38: | Line 45: |
* Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) * Make gstlal-calibration running on a machine at KAGRA (DT, SH) * Use gstlal-calibration for the offline h(t) reconstruction of bKAGRA phase-1 data (ST, DT) * Generation of FIR filters for KAGRA DARM model (ST, DT) * Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) |
* Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ''ongoing'' | expected finish: '''N/A'''] * Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ''ongoing'' | expected finish: '''Jul 15'''] * --(Find names and versions of all prerequisite libraries)-- [[KAGRA/Subgroups/CAL/WG/offline/gstlal|gstlal installation]] * --(Install prerequisites and gstlal-cal package on a machine at AS)-- * Test gstlal-cal pipeline on an AS machine * --(Install prerequisites and gstlal-cal package on a machine at KAGRA)-- [[KAGRA/Subgroups/CAL/WG/offline/gstlal|gstlal installation]] * Test the pipeline on a KAGRA machine [[KAGRA/Subgroups/CAL/WG/offline/tests|gstlal tests]] * Use gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data (SH, ST, DT) [status: ''to do'' | expected finish: '''Aug 15'''] * Note: depends on the installation of gstlal-cal on a machine at AS and at KAGRA * Produce dummy output equivalent to online cal output (at AS) * Compare gstlal and online outputs of bKAGRA phase-1 data (at KAGRA) [[KAGRA/Subgroups/CAL/WG/offline/phase-1|phase-1 data processing]] * Use gstlal-calibration for the better offline h(t) reconstruction from bKAGRA phase-1 data (ST, DT) [status: ''to do'' | expected finish: '''Oct 1'''] * Note: depends on the completion of using gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data * Generate simple FIR filters to compensate AA/AI effects at high frequencies * Compare better gstlal (this task), gstlal dummy (previous task) and online outputs of bKAGRA phase-1 data * Generate an initial version of the status vector (DT, ST, SH) [status: ''to do'' | expected finish: '''Sep 15'''] * Decide status vector bits * Note: Status vector bits will be updated after deciding which of the time-dependent parameters are calculated and which of them are applied. * Modify (adapt) the function that generates the status vector * Produce the status vector for bKAGRA phase-1 data * Apply corrections for temporal variations in the DARM (DT, ST, SH) [status: ''to do'' | expected start: '''Oct 1''' | expected finish: '''bKAGRA phase-2'''] * Calculate time-dependent parameters * Study/improve averaging of the parameter values * Incorporate goodness of the parameters into the status vector bits * Use bKAGRA phase-2 data to study averaging / goodness-thresholds of the parameter values * Generation of FIR filters for KAGRA DARM model (ST, DT) [status: ''to do'' | expected finish: '''end of bKAGRA phase-2'''] * Note: Depends on the readiness of the DARM model * Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) [status: ''to do'' | expected finish: '''end of bKAGRA phase-2'''] * Note: Depends on the readiness of DMT * Run run the pipeline in low-latency during bKAGRA phase-2 |
Line 44: | Line 76: |
=== DARM model (T.Yamamoto,..., D.Tuyenbayev) === * Make a subway map of the KAGRA DARM model * Optimize the calibration lines * Coordinate the Open Loop Gain (OLG) Transfer function measurements * Estimate and trace the slow time variation of the calibration parameters * Electronics transfer function. |
=== DARM model (T.Yamamoto, D.Tuyenbayev, T.Yokozawa) === * Make a subway map of the KAGRA DARM model [status: ''to do'' | expected finish: '''Sep. 1, 2018'''] * Optimize the calibration lines [status: ''to do'' | expected finish: '''May 1, 2019'''] * DARM sensitivity is required in order to optimize. * Coordinate the Open Loop Gain (OLG) Transfer function measurements [status: ''to do'' | expected finish: '''Apr. 1, 2019'''] * DARM lock is required because this task contains try and error of the swept sine injection. * Estimate and trace the slow time variation of the calibration parameters [status: ''to do'' | expected finish: '''Jun. 1, 2019'''] * Electronics transfer function. [status: ''to do'' | expected finish: '''Oct. 1, 2018'''] * The subway map help us to decide the necessary component. === Verification of Calibration (Y.Inoue, C.Bill, W.Ogaki) === * Coordinate h(t) calibration with the Free-swinging Michelson method [status: ''to do'' | expected finish: '''May. 1, 2019'''] * Compare h(t)s calibrated between Free-swinging Michelson and Pcal[status: ''to do'' | expected finish: '''May. 1, 2019'''] * Compare h(t)s calculated between diff,common,...[status: ''to do'' | expected finish: '''May. 1, 2019'''] |
Line 51: | Line 90: |
=== Pcal verification (Y.Inoue,...) === * Coordinate h(t) calibration with the Free-swinging Michelson method * Compare h(t)s calibrated between Free-swinging Michelson and Pcal * Compare h(t)s calculated between diff,common,... |
=== Hardware injection (T.Yokozawa,S.Haino,Cory ) === * Make the online model for the hardware injection with actuators[status: ''fist version finished'' | expected finish: '''end of August'''] * Make the online model for the hardware injection with Pcal[status: ''fist version finished'' | expected finish: '''end of August'''] * Coordinate the hardware injection tests[status: ''to do'' | expected finish: '''end of bKAGRA phase-2'''] * Analyze the hardware injected data and verify the DARM subway map[status: ''to do'' | expected finish: '''end of bKAGRA phase-2'''] |
Line 56: | Line 96: |
=== Hardware injection (T.Yokozawa, Cory, ) === * Make the online model for the hardware injection with actuators * Make the online model for the hardware injection with Pcal * Coordinate the hardware injection tests * Analyze the hardware injected data and verify the DARM subway map |
=== Systematic errors assignment (T.Sawada, Y.Inoue, T.Yokozawa, K.Izumi,S.Haino) === * Goal: Estimate the systematic errors due to calibration * Details: * Estimate the value of calibration uncertainties(maximum and minimum of errors with +-1sigma uncertainties) for magnitude[%] and phase[deg.] (TS) [status: ''to do'' | expected finish: '''end of Jul'''] |
Line 62: | Line 101: |
=== Systematic errors assignment (T.Sawada, Y.Inoue, S.Haino) === * Estimate the systematic errors due to calibration |
* Estimate the total calibration error and uncertainty envelope with respect to the frequency (TS) [status: ''to do'' | expected finish: '''end of Jul'''] * Then Provide them to the data analysis group and simulation group |
Line 65: | Line 106: |
* Provide the number (amplitude and phase) for the data analysis group | |
Line 67: | Line 107: |
* (If possible) Incorporate DARM model and parameter uncertainties in the data analysis | * (If possible) Incorporate DARM model and parameter uncertainties in the data analysis * A.Miyamoto will show the first results of the effect of calibration uncertainties to the POP III data analysis |
Calibration Tasks and Milestones (Towards O3)
Goals
- Make the whole chain of h(t) reconstruction running with Pcal
- 3 types of h(t) provide (online, low latency, offline)
- online h(t) generation using Pcal(DGS)
- low latency and offline will be similar code
- Accuracy at the initial LIGO O1 level (10%,10deg.)
- LIGO also have many try and error
- free sweging is used for calibration method comparison
- final goal is 1%, 1deg.
- By the starting of phase-2 engineering run (well in advance of joining O3)
Task (Responsible and sub-responsible person(s))
Cross out if the tasks are completed
Listing-up (S.Haino and responsible people)
List-up tasks and responsible person
List-up milestones and deadline
Submit the list of task and milestone to the KAGRA scheduler
Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua,c.Bill)
Install Pcal at X and Y-end and coordinate[status: on going | expected finish: Sep. 1, 2018]
the long-term Pcal characterization [status: to do | expected finish: Sep. 1, 2018]
Prepare for the necessary EPICS channels to the online system for the calibration
List-up the systematic error budget table for O3 [status: on going | expected finish: until O3]
Achieve 1% displacement error [status: to do | expected finish: Apr. 1, 2019]
Absolute power calibration[status: to do | expected finish: Jan. 1, 2019]
- Note: Maintenance at Kamioka site.
- BH should stay Kamioka and periodic work
- Telephoto camera
- Installation is almost done
- Maintenance of TCam is done by T.Yokozawa
- IR filter issue(spare camera), additional spare camera.
- Image analysis by Tomigami.
Front-end (T.Yamamoto, T.Sawada)
Make the models for the online h(t) reconstruction [status: ongoing | expected finish: Jan. 1, 2019]
Provide the necessary DAQ channels for the low-latency calibration[status: ongoing | expected finish: Jan. 1, 2019]
- The necessary channels had already existed in Phase-1 operation (What we should are only small fix.).
- ...
Low-latency and offline (D.Tuyenbayev, S.Tsuchida, S.Haino)
Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ongoing | expected finish: N/A]
Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ongoing | expected finish: Jul 15]
Find names and versions of all prerequisite libraries gstlal installation
Install prerequisites and gstlal-cal package on a machine at AS
- Test gstlal-cal pipeline on an AS machine
Install prerequisites and gstlal-cal package on a machine at KAGRA gstlal installation
Test the pipeline on a KAGRA machine gstlal tests
Use gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data (SH, ST, DT) [status: to do | expected finish: Aug 15]
- Note: depends on the installation of gstlal-cal on a machine at AS and at KAGRA
- Produce dummy output equivalent to online cal output (at AS)
Compare gstlal and online outputs of bKAGRA phase-1 data (at KAGRA) phase-1 data processing
Use gstlal-calibration for the better offline h(t) reconstruction from bKAGRA phase-1 data (ST, DT) [status: to do | expected finish: Oct 1]
- Note: depends on the completion of using gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data
- Generate simple FIR filters to compensate AA/AI effects at high frequencies
- Compare better gstlal (this task), gstlal dummy (previous task) and online outputs of bKAGRA phase-1 data
Generate an initial version of the status vector (DT, ST, SH) [status: to do | expected finish: Sep 15]
- Decide status vector bits
- Note: Status vector bits will be updated after deciding which of the time-dependent parameters are calculated and which of them are applied.
- Modify (adapt) the function that generates the status vector
- Produce the status vector for bKAGRA phase-1 data
- Decide status vector bits
Apply corrections for temporal variations in the DARM (DT, ST, SH) [status: to do | expected start: Oct 1 | expected finish: bKAGRA phase-2]
- Calculate time-dependent parameters
- Study/improve averaging of the parameter values
- Incorporate goodness of the parameters into the status vector bits
- Use bKAGRA phase-2 data to study averaging / goodness-thresholds of the parameter values
Generation of FIR filters for KAGRA DARM model (ST, DT) [status: to do | expected finish: end of bKAGRA phase-2]
- Note: Depends on the readiness of the DARM model
Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) [status: to do | expected finish: end of bKAGRA phase-2]
- Note: Depends on the readiness of DMT
- Run run the pipeline in low-latency during bKAGRA phase-2
DARM model (T.Yamamoto, D.Tuyenbayev, T.Yokozawa)
Make a subway map of the KAGRA DARM model [status: to do | expected finish: Sep. 1, 2018]
Optimize the calibration lines [status: to do | expected finish: May 1, 2019]
- DARM sensitivity is required in order to optimize.
Coordinate the Open Loop Gain (OLG) Transfer function measurements [status: to do | expected finish: Apr. 1, 2019]
- DARM lock is required because this task contains try and error of the swept sine injection.
Estimate and trace the slow time variation of the calibration parameters [status: to do | expected finish: Jun. 1, 2019]
Electronics transfer function. [status: to do | expected finish: Oct. 1, 2018]
- The subway map help us to decide the necessary component.
Verification of Calibration (Y.Inoue, C.Bill, W.Ogaki)
Coordinate h(t) calibration with the Free-swinging Michelson method [status: to do | expected finish: May. 1, 2019]
Compare h(t)s calibrated between Free-swinging Michelson and Pcal[status: to do | expected finish: May. 1, 2019]
Compare h(t)s calculated between diff,common,...[status: to do | expected finish: May. 1, 2019]
Hardware injection (T.Yokozawa,S.Haino,Cory )
Make the online model for the hardware injection with actuators[status: fist version finished | expected finish: end of August]
Make the online model for the hardware injection with Pcal[status: fist version finished | expected finish: end of August]
Coordinate the hardware injection tests[status: to do | expected finish: end of bKAGRA phase-2]
Analyze the hardware injected data and verify the DARM subway map[status: to do | expected finish: end of bKAGRA phase-2]
Systematic errors assignment (T.Sawada, Y.Inoue, T.Yokozawa, K.Izumi,S.Haino)
- Goal: Estimate the systematic errors due to calibration
- Details:
Estimate the value of calibration uncertainties(maximum and minimum of errors with +-1sigma uncertainties) for magnitude[%] and phase[deg.] (TS) [status: to do | expected finish: end of Jul]
Estimate the total calibration error and uncertainty envelope with respect to the frequency (TS) [status: to do | expected finish: end of Jul]
- Then Provide them to the data analysis group and simulation group
- Make a simulation.
- Provide the calibration envelopes for the data analysis group
- (If possible) Incorporate DARM model and parameter uncertainties in the data analysis
- A.Miyamoto will show the first results of the effect of calibration uncertainties to the POP III data analysis