Calibration Tasks and Milestones (Towards O3)

Goals

  • Make the whole chain of h(t) reconstruction running with Pcal
    • 3 types of h(t) provide (online, low latency, offline)
    • online h(t) generation using Pcal(DGS)
    • low latency and offline will be similar code
  • Accuracy at the initial LIGO O1 level (10%,10deg.)
    • LIGO also have many try and error
    • free sweging is used for calibration method comparison
    • final goal is 1%, 1deg.
  • By the starting of phase-2 engineering run (well in advance of joining O3)

Task (Responsible and sub-responsible person(s))

  • Cross out if the tasks are completed

Listing-up (S.Haino and responsible people)

  • List-up tasks and responsible person

  • List-up milestones and deadline

  • Submit the list of task and milestone to the KAGRA scheduler

Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua,c.Bill)

PcalTask

  • Install Pcal at X and Y-end and coordinate[status: on going | expected finish: Sep. 1, 2018]

  • the long-term Pcal characterization [status: to do | expected finish: Sep. 1, 2018]

  • Prepare for the necessary EPICS channels to the online system for the calibration

  • List-up the systematic error budget table for O3 [status: on going | expected finish: until O3]

  • Achieve 1% displacement error [status: to do | expected finish: Apr. 1, 2019]

  • Absolute power calibration[status: to do | expected finish: Jan. 1, 2019]

  • Note: Maintenance at Kamioka site.
    • BH should stay Kamioka and periodic work
    • Telephoto camera
      • Installation is almost done
      • Maintenance of TCam is done by T.Yokozawa
      • IR filter issue(spare camera), additional spare camera.
      • Image analysis by Tomigami.

Front-end (T.Yamamoto, T.Sawada)

  • Make the models for the online h(t) reconstruction [status: ongoing | expected finish: Jan. 1, 2019]

  • Provide the necessary DAQ channels for the low-latency calibration[status: ongoing | expected finish: Jan. 1, 2019]

    • The necessary channels had already existed in Phase-1 operation (What we should are only small fix.).
  • ...

Low-latency and offline (D.Tuyenbayev, S.Tsuchida, S.Haino)

  • Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ongoing | expected finish: N/A]

  • Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ongoing | expected finish: Jul 15]

    • Find names and versions of all prerequisite libraries gstlal installation

    • Install prerequisites and gstlal-cal package on a machine at AS

    • Test gstlal-cal pipeline on an AS machine
    • Install prerequisites and gstlal-cal package on a machine at KAGRA gstlal installation

    • Test the pipeline on a KAGRA machine gstlal tests

  • Use gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data (SH, ST, DT) [status: to do | expected finish: Aug 15]

    • Note: depends on the installation of gstlal-cal on a machine at AS and at KAGRA
    • Produce dummy output equivalent to online cal output (at AS)
    • Compare gstlal and online outputs of bKAGRA phase-1 data (at KAGRA) phase-1 data processing

  • Use gstlal-calibration for the better offline h(t) reconstruction from bKAGRA phase-1 data (ST, DT) [status: to do | expected finish: Oct 1]

    • Note: depends on the completion of using gstlal-calibration for the initial offline h(t) reconstruction from bKAGRA phase-1 data
    • Generate simple FIR filters to compensate AA/AI effects at high frequencies
    • Compare better gstlal (this task), gstlal dummy (previous task) and online outputs of bKAGRA phase-1 data
  • Generate an initial version of the status vector (DT, ST, SH) [status: to do | expected finish: Sep 15]

    • Decide status vector bits
      • Note: Status vector bits will be updated after deciding which of the time-dependent parameters are calculated and which of them are applied.
    • Modify (adapt) the function that generates the status vector
    • Produce the status vector for bKAGRA phase-1 data
  • Apply corrections for temporal variations in the DARM (DT, ST, SH) [status: to do | expected start: Oct 1 | expected finish: bKAGRA phase-2]

    • Calculate time-dependent parameters
    • Study/improve averaging of the parameter values
    • Incorporate goodness of the parameters into the status vector bits
    • Use bKAGRA phase-2 data to study averaging / goodness-thresholds of the parameter values
  • Generation of FIR filters for KAGRA DARM model (ST, DT) [status: to do | expected finish: end of bKAGRA phase-2]

    • Note: Depends on the readiness of the DARM model
  • Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) [status: to do | expected finish: end of bKAGRA phase-2]

    • Note: Depends on the readiness of DMT
    • Run run the pipeline in low-latency during bKAGRA phase-2

DARM model (T.Yamamoto, D.Tuyenbayev, T.Yokozawa)

  • Make a subway map of the KAGRA DARM model [status: to do | expected finish: Sep. 1, 2018]

  • Optimize the calibration lines [status: to do | expected finish: May 1, 2019]

    • DARM sensitivity is required in order to optimize.
  • Coordinate the Open Loop Gain (OLG) Transfer function measurements [status: to do | expected finish: Apr. 1, 2019]

    • DARM lock is required because this task contains try and error of the swept sine injection.
  • Estimate and trace the slow time variation of the calibration parameters [status: to do | expected finish: Jun. 1, 2019]

  • Electronics transfer function. [status: to do | expected finish: Oct. 1, 2018]

    • The subway map help us to decide the necessary component.

Verification of Calibration (Y.Inoue, C.Bill, W.Ogaki)

  • Coordinate h(t) calibration with the Free-swinging Michelson method [status: to do | expected finish: May. 1, 2019]

  • Compare h(t)s calibrated between Free-swinging Michelson and Pcal[status: to do | expected finish: May. 1, 2019]

  • Compare h(t)s calculated between diff,common,...[status: to do | expected finish: May. 1, 2019]

Hardware injection (T.Yokozawa,S.Haino,Cory )

  • Make the online model for the hardware injection with actuators[status: fist version finished | expected finish: end of August]

  • Make the online model for the hardware injection with Pcal[status: fist version finished | expected finish: end of August]

  • Coordinate the hardware injection tests[status: to do | expected finish: end of bKAGRA phase-2]

  • Analyze the hardware injected data and verify the DARM subway map[status: to do | expected finish: end of bKAGRA phase-2]

Systematic errors assignment (T.Sawada, Y.Inoue, T.Yokozawa, K.Izumi,S.Haino)

  • Goal: Estimate the systematic errors due to calibration
  • Details:
    • Estimate the value of calibration uncertainties(maximum and minimum of errors with +-1sigma uncertainties) for magnitude[%] and phase[deg.] (TS) [status: to do | expected finish: end of Jul]

    • Estimate the total calibration error and uncertainty envelope with respect to the frequency (TS) [status: to do | expected finish: end of Jul]

    • Then Provide them to the data analysis group and simulation group
  • Make a simulation.
  • Provide the calibration envelopes for the data analysis group
  • (If possible) Incorporate DARM model and parameter uncertainties in the data analysis
    • A.Miyamoto will show the first results of the effect of calibration uncertainties to the POP III data analysis