Meetings
- Meeting time: 11:00-11:30 JST/KST on every Wednesday
- Meeting room: Zoom3
Contents
20260318 (Wed.)
- Agenda
- Announcement
- Scheduled conference
LVK meeting: 2026/3/9-13 @Pisa Italy web 03/09 OPS session
- JPS meeting: 2026/03/16-19 online
- KIW14: 2026/05/14-16 @Perugia, Italy
GWADW: 2026/05/17-23 @Elba web
KAGRA site report 02/16
- From April, the maintanance day at KAGRA site will be shifted from Friday to Monday.
- Evaluation of effort for authorship 2025 is underway.
- Next meeting: middle of April (the meeting time might be changed)
Upgrade DetChar computers (YamaT)
- DQR update (Yuzurihara)
lock loss study in the commissioning (YamaT, Yuzurihara) web
- Update contents of summary page (Oshino)
- Related to segment files (Uchikata, Narikawa)
- pyCBC trigger list for O4a data (Narikawa and Uchikata)
- provide the CAT1 veto-definer file for IPC glitch (Uchikata)
- Scheduled conference
- Announcement
- Minutes
- Commissioning
- Planned power outage at Kamioka
Shutdown of detchar computers located in the mine (Yuzurihara)
- The detchar computers (k1det0, k1det1) came back online from the power outage. The regular production of the segment files at k1det1 restarted without issues.
Preparation for the upgrade of Pastavi server
- The new Pastavi server was purchased with the SEO budget and delivered to the KAGRA site. I finished the initial setup on the server and confirmed that Pastavi works well. After that, I sent it to Kashiwa. I will replace the server in Kashiwa this Thursday.
20260225 (Wed.)
- Agenda
- Announcement
- Scheduled conference
LVK meeting: 2026/3/9-13 @Pisa Italy web, the deadline for poster registration is 8 Feb.
- JPS meeting: 2026/03/16-19 online
- KIW14: 2026/05/14-16 @Perugia, Italy
- GWADW: 2026/05/17-23 @Elba
KAGRA site report 02/16
- From April, the maintanance day at KAGRA site will be shifted from Friday to Monday.
02/04 Xarm and Yarm round-trip loss measurements using POP and POS
02/05 Continuation of high-bandwidth ASC work: CHARD_P / DHARD_P
02/18 Local control noise coupling is reduced after warming up
- Next meeting: 2026/03/18
- Scheduled conference
- Progress reports
Upgrade DetChar computers (YamaT)
- DQR update (Yuzurihara)
lock loss study in the commissioning (YamaT, Yuzurihara) web
- Update contents of summary page (Oshino)
- Related to segment files (Uchikata, Narikawa)
- pyCBC trigger list for O4a data (Narikawa and Uchikata)
- provide the CAT1 veto-definer file for IPC glitch (Uchikata)
- Announcement
- Minutes
- Commissioning
- The updated segment file for O4a and O4c are prepared. (Uchikata)
- Yuzurihara performed the review as a cross check of the prepared segment files.
- Upgrade of Pastavi server (Yuzurihara)
- New server was delibered to KAGRA site. The initial setting for the server is underway. The Pastavi server at Kashiwa will be replaced on middle of March.
20260204 (Wed.)
- cancel
20260128 (Wed.)
- Agenda
- Announcement
- Scheduled conference
LVK meeting: 2026/3/9-13 @Pisa Italy web, the deadline for poster registration is 8 Feb.
- JPS meeting: 2026/03/16-19 online
- KIW14: 2026/05/14-16 @Perugia, Italy
- GWADW: 2026/05/17-23 @Elba
KAGRA site report 01/14
- Next meeting: 2026/02/04, 2/25
- Scheduled conference
- Progress reports
Upgrade DetChar computers (YamaT)
- DQR update (Yuzurihara)
lock loss study in the commissioning (YamaT, Yuzurihara) web
- Update contents of summary page (Oshino)
- Related to segment files (Uchikata, Narikawa)
- pyCBC trigger list for O4a data (Narikawa and Uchikata)
- provide the CAT1 veto-definer file for IPC glitch (Uchikata)
- Announcement
- Minutes
- Commissioning
- Method to identify scattered light noise
- Chia-Jui Chou will give a presentation about the algorithm to identify the scattered light noise.
- The review of the updated segment file for O4a and O4c is necessary.
- The segment files were prepared by Uchikata-san and stored in kmst-2. Yuzurihara plan to review them.
20260114 (Wed.)
- Agenda
- Announcement
- O4 schedule:
- O4 observing run ended at 1:00 JST 11/19. Thank you for many contributions!
Run plan (11/18) operation call (01/08) LIGO detchar (01/12)
- Scheduled conference
JGRG34: 2026/01/19~23 @Kyoto university web
- LVK meeting: 2026/3/9-13 @Pisa Italy
KAGRA site report 12/22
- Next meeting: 2026/01/28
- O4 schedule:
- Progress reports
Upgrade DetChar computers (YamaT)
- DQR update (Yuzurihara)
lock loss study in the commissioning (YamaT, Yuzurihara) web
- Update contents of summary page (Oshino)
- Related to segment files (Uchikata, Narikawa)
- pyCBC trigger list for O4a data (Narikawa and Uchikata)
- provide the CAT1 veto-definer file for IPC glitch (Uchikata)
- Announcement
- Minutes
- Commissioning
Upload of Segment files to DQSEGDB git issue
- Upgrade of Pastavi server (Yuzurihara)
- New server will be delibered to KAGRA site next week. After the initial setting, the Pastavi server at Kashiwa will be replaced. (CPU 10 cores, memory 256 GB)