* Meeting time: 14:00-15:00 JST/KST on every Thursday * Meeting room: Zoom3 (https://zoom.us/j/5045179604) |
* Meeting time: 11:00-11:30 JST/KST on every Wednesday * Meeting room: Zoom3 |
Line 9: | Line 9: |
=== 20200402 (Thu.) === * Agenda: * File server status * SummaryPage * Omicron trigger generation * Segment Information * KISTI results capability * Observing run * GlitchPlot for burst analysis * DetChar DQ shift * Update for O4 plan |
|
Line 21: | Line 10: |
=== 20200326 (Thu.) === * Agenda: * Commissioning situation * Commissioning test will be continued until Mar. 31st * During Apr. 1st to 7th, engineering run will be performed. * After Apr. 7th, we have a two weeks observing run (only KAGRA) * If LIGO, and Virgo will come back to observing run, we will aim to join O3. * SummaryPage (RAID trouble) * File server has a disk problem. * RAID system is now being rebuilt. (It will be finished today's evening.) * GlitchPlot for Burst evnet triggers * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11571|JGW-G2011571]] * DetChar pipelines on KISTI * Code update of CAGMon * === 20200312 (Thu.) === * Agenda: * Current status of site (commissioning) activities * Commissioning break was started from 10th Mar. It continues until 24th Mar. * Joinning O3 should be discussed on JRPC meeting on 26th Mar.(?). * Update of DQ state vector * Science mode during 25th Feb. - 10th Mar. didn't include SDF flags. * I updated to contain the SDF flags as the one of the condition of the Science mode. * Automation plan of GlitchPlot for GW event alert * We plan to move GlitchPlot from ICRR cluster to Kamioka computers. * Requirement: * Disk: 100MB/event * CPU: ??? * Data transfer to KISTI * ER on Dec. data was transferred. * Many tools is already available on KISTI cluster. * Announce about LVK session * We plan to have DetChar telecons instead of LVK meeting. * TY circulate concrete date and time on ML after deciding. === 20200305 (Thu.) === * Agenda: * Observing run status * Binary range is ~400kpc (Best is 500kpc.) * Trigger rate check * Quite difference Trigger rate between the strain signal and the error signal. * Glitch plot with Burst triggers. * SummaryPage troubles * Some process (LSC.ini) was frequently stopped. * RRT tools * Shinkai-san suggested us it's better to prepare the dedicated workstation and mail address. * RRT tools from medm interface is available at Kamioka site * LValert can be receive alert from GraceDB. * Event information is not enough (no mass parameter). * Tagoshi-san tested on Kashiwa server. |
----- === 20240207 (Wed.) === * Agenda * Announcement * KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 [[https://indico.phys.sinica.edu.tw/event/92/|web]] * Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 [[https://indico.phys.sinica.edu.tw/event/92/page/220-gravitational-wave-open-data-workshop|web]] * O4a/preO4b(not call it as postO4a)/ER16/O4b schedule: * '''ER16''': It will nominally start on '''13 Mar 2024''', and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.) * '''O4b''': We plan to commence O4b at 1600 UTC (2500 JST) on '''27 Mar 2024'''. * Ref.[[https://wiki.ligo.org/Operations/Agenda231214#Agenda|internal short announcements (reminders)]], [[https://observing.docs.ligo.org/plan/|public announcements]] * White paper and task list for 2024 [[https://git.ligo.org/operations/operations-white-paper-2023|git repo]] * LVK meeting on March 11-14 at Louisiana State University [[https://www.lsu.edu/physics/lvkmeeting/|web]] * Early Registration is open until February 1 * There is no fee for online participants * Update of member list for DetChar mailing list * KAGRA site report (Yuzurihara) * Commissioning support + tasks related to O4a * O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST * Event validation (YamaT) * Online data quality state vector (YamaT) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28498|model update of k1detdq0]] * Tool to evaluate Gaussianity (Yamamura) * Scattered light noise (Yamamura) * Pastavi update (Yuzurihara) * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * Classification of glitch noise (Shikano, Oshino) * IPC glitch * line noise study (Samurai) * Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT) * DQR update (Yuzurihara) * Update contents of summary page (Oshino) * Combine DET computer resources into one DET cluster at Kamioka site * Related to segment files (Uchikata, Narikawa) * provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) [[https://ldas-jobs.ligo.caltech.edu/~detchar/summary/O4a/|O4a (LV)]] * Minutes |
Line 74: | Line 47: |
=== 20200227 (Thu.) === * Agenda: * SummaryPage trouble * Configuration file errors -> fixed and checking now (Oshino-san) * Past two day's pages will be regenerated. * RRT * Short-time SummaryPage generator tool on MEDM. * lvalert may be already available for KAGRA. * We can receive RRT call by setting 'GCN PRELIM SENT'. * DQ shift * This taks should be assigned for collaborator shift. * TY will discuss this issue with Miyoki-san. |
----- === 20240131 (Wed.) === * Agenda * Announcement * KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 [[https://indico.phys.sinica.edu.tw/event/92/|web]] * Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 [[https://indico.phys.sinica.edu.tw/event/92/page/220-gravitational-wave-open-data-workshop|web]] * O4a/preO4b(not call it as postO4a)/ER16/O4b schedule: * '''ER16''': It will nominally start on '''13 Mar 2024''', and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.) * '''O4b''': We plan to commence O4b at 1600 UTC (2500 JST) on '''27 Mar 2024'''. * Ref.[[https://wiki.ligo.org/Operations/Agenda231214#Agenda|internal short announcements (reminders)]], [[https://observing.docs.ligo.org/plan/|public announcements]] * White paper and task list for 2024 [[https://git.ligo.org/operations/operations-white-paper-2023|git repo]] * LVK meeting on March 11-14 at Louisiana State University [[https://www.lsu.edu/physics/lvkmeeting/|web]] * Early Registration is open until February 1 * There is no fee for online participants * Update of member list for DetChar mailing list * LVK MoA survey summary [[https://dcc.ligo.org/G2400189|LIGO DCC]] * KAGRA site report (Yuzurihara) * Commissioning support + tasks related to O4a * O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST * Event validation (YamaT) * Tool to evaluate Gaussianity (Yamamura) * Scattered light noise (Yamamura) * Pastavi update (Yuzurihara) * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * Classification of glitch noise (Shikano, Oshino) * IPC glitch * line noise study (Samurai) * Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT) * DQR update (Yuzurihara) * Update contents of summary page (Oshino) * Combine DET computer resources into one DET cluster at Kamioka site * Related to segment files (Uchikata, Narikawa) * provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) [[https://ldas-jobs.ligo.caltech.edu/~detchar/summary/O4a/|O4a (LV)]] * Minutes * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28392|O4a hveto results]] * line noise study (Samurai) * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=15613|slide]] * Is it possible to set the initial parameter in advance, such as prominence and height? * In future, it is better to extend the fft length to be longer for fine frequency resolution. * Update contents of summary page (Oshino) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28397|Update configuration file on SummaryPage]] * Related to segment files (Uchikata, Narikawa) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28399|Glitch rate for O4a]] * provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) [[https://ldas-jobs.ligo.caltech.edu/~detchar/summary/O4a/|O4a (LV)]] * The attempt to generate summary page is on system-B. For reading data, NDS2 server is helpful. |
Line 87: | Line 94: |
----- === 20240124 (Wed.) === * Agenda * Announcement * KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 * Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 [[https://gwosc.org/workshops/|web]] * LIGO-Virgo-KAGRA detchar joint meeting * tileslot: onthly, 23:00 JST (14:00 UTC) or 6:00 JST (21 UTC) * Last meeting on Nov. 15 23:00 JST (14:00 UTC) [[https://wiki.ligo.org/DetChar/Telecon20231115|wiki]] * O4a/preO4b(not call it as postO4a)/ER16/O4b schedule: * '''O4a''': It will end at 1600 UTC on '''16 Jan 2024'''. LLO will end O4a observing early, at 1400 UTC. * '''ER16''': It will nominally start on '''13 Mar 2024''', and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.) * '''O4b''': We plan to commence O4b at 1600 UTC (2500 JST) on '''27 Mar 2024'''. * Ref.[[https://wiki.ligo.org/Operations/Agenda231214#Agenda|internal short announcements (reminders)]], [[https://observing.docs.ligo.org/plan/|public announcements]] * Information of O4a [[https://dac.icrr.u-tokyo.ac.jp/KAGRA/Observations/O4a|wiki]] page * White paper and task list for 2024 [[https://git.ligo.org/operations/operations-white-paper-2023|git repo]] * LVK meeting on March 11-14 at Louisiana State University * Update of member list for DetChar mailing list * KAGRA site report (Yuzurihara) * Commissioning support + tasks related to O4a * O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST * Event validation (YamaT) * Tool to evaluate Gaussianity (Yamamura) * Scattered light noise (Yamamura) * Pastavi update (Yuzurihara) * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * Classification of glitch noise (Shikano, Oshino) * IPC glitch * line noise study (Samurai) * Peak identifications [[https://gwdet.icrr.u-tokyo.ac.jp/~controls/misc/html/knownlines_o4a.html|web]] * Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT) * DQR update (Yuzurihara) * Update contents of summary page (Oshino) * run Omicron at Kamioka site and refresh the Omicron plots on summary page during O4a period * Combine DET computer resources into one DET cluster at Kamioka site * Script to generate segment files (Uchikata, Narikawa) * Related to segment files (Uchikata, Narikawa) * provide the dedicated summary page for O4a of KAGRA? [[https://ldas-jobs.ligo.caltech.edu/~detchar/summary/O3a/|O3a (LV)]] * Minutes * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28392|O4a hveto results]] * Update contents of summary page (Oshino) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28390|Modified configuration file on SummaryPage]] |
|
Line 88: | Line 138: |
=== 20200130 (Thu.) === * Agenda: * KAGRA Readiness * RRT shift * PEM DQ flags |
----- === 20240117 (Wed.) === * Agenda * Announcement * KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 * Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 [[https://gwosc.org/workshops/|web]] * LIGO-Virgo-KAGRA detchar joint meeting * tileslot: onthly, 23:00 JST (14:00 UTC) or 6:00 JST (21 UTC) * Last meeting on Nov. 15 23:00 JST (14:00 UTC) [[https://wiki.ligo.org/DetChar/Telecon20231115|wiki]] * O4a/preO4b(not call it as postO4a)/ER16/O4b schedule: * '''O4a''': It will end at 1600 UTC on '''16 Jan 2024'''. LLO will end O4a observing early, at 1400 UTC. * '''ER16''': It will nominally start on '''13 Mar 2024''', and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.) * '''O4b''': We plan to commence O4b at 1600 UTC (2500 JST) on '''27 Mar 2024'''. * Ref.[[https://wiki.ligo.org/Operations/Agenda231214#Agenda|internal short announcements (reminders)]], [[https://observing.docs.ligo.org/plan/|public announcements]] * Information of O4a [[https://dac.icrr.u-tokyo.ac.jp/KAGRA/Observations/O4a|wiki]] page * White paper and task list for 2024 [[https://git.ligo.org/operations/operations-white-paper-2023|git repo]] * LVK meeting on March 11-14 at Louisiana State University * KAGRA site report (Yuzurihara) * Commissioning support + tasks related to O4a * O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST * Event validation (YamaT) * Tool to evaluate Gaussianity (Yamamura) * Scattered light noise (Yamamura) * Pastavi update (Yuzurihara) * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * Classification of glitch noise (Shikano, Oshino) * IPC glitch * line noise study (Samurai) * Peak identifications [[https://gwdet.icrr.u-tokyo.ac.jp/~controls/misc/html/knownlines_o4a.html|web]] * Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT) * DQR update (Yuzurihara) * Update contents of summary page (Oshino) * run Omicron at Kamioka site and refresh the Omicron plots on summary page during O4a period * Combine DET computer resources into one DET cluster at Kamioka site * Script to generate segment files (Uchikata, Narikawa) * Related to segment files (Uchikata, Narikawa) * provide the dedicated summary page for O4a of KAGRA? [[https://ldas-jobs.ligo.caltech.edu/~detchar/summary/O3a/|O3a (LV)]] * Minutes * Tool to evaluate Gaussianity (Yamamura) * Gauch recently looks not running. There is no html page linked from summary page. We will check the details later. * DQR update (Yuzurihara) * I asked the remote help to Derek. I'm submitteing the application for the ICRR computer account. * IPC glitch * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28025|Summary of recent segment for IPC glitch (2023/11~12)]] * Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28194|2023-05-24 ~ 06-07 O4a hveto results]] * The analysis for the remained date will be * Update contents of summary page (Oshino) * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28057|Modified configuration files of SummaryPage]] * [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=28247|Modified configuration file on SummaryPage]] |
Line 94: | Line 189: |
=== 20200116 (Thu.) === * Agenda: * Minimum goal of KAGRA readiness issue * State Vector definition * goal: send {{{K1:DET-DQ_STATE_VECTOR}}} * status: Done. * DQSEGDB capability * goal: send OBSERVATION segment * status: 95% Automation should be done. (will be done by Robert) * Web page preparation * goal: publish SummaryPage * status: Done. * DQ event validation * under discussion Probably we cannot provide so many veto segments.<<BR>> So at least one (hopefully a few) simple segments will be provided and uploaded.<<BR>> (e.g. Omicron triggered segments, Earthquake segments, etc.) * GraceDB issue * under discussion Full(?) access to GraceDB is opened for KAGRA people.<<BR>> Developing/importing GraceDB API tools is better to be done with DET and DAWG. === 20200109 (Thu.) === * Agenda: * KAGRA readiness issue * State Vector definition * SV is provided on the real-time IFO control model. * SV is contained in both raw frames and low-latency frames. * SV definition is summarized on [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/DataQuality|Wiki]] and kept as latest information. * Finally it should be summarized as a tech-report. * DQSEGDB capability * Segment files are provided on the Kamioka and Kashiwa servers. * Files will be shared with LV by rsync+ssh method. * Accessing gwdet.icrr.u-tokyo.ac.jp from LIGO's DQSEGDB was already successfully. * Web page preparation * SummaryPage is opened also for remote site people. * Contents are being closed to LIGO's SummaryPage contents. * TY and Alex are now updating some softwares on k1sum0. So SummaryPage may become unstable next couple of days. * DetChar/DQ event validataion * We are now planning to provide DQ flags indicating earthquake, loud seismotion, etc. (See Kozakai-san's slide) * These information are shared with LV via DQSEGDB. * Low-Latency tools and GraceDB issues * Some tools used as low-latency ones in LIGO (Omicron, hveto etc.) are available. * We are waiting for the update of GraceDB authentication by LIGO. * Offline DQ [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11176}|Slides]] * E-run analysis (washimi) [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11177|Slide]] === 20191121 (Tue.) === * Agenda: * Offline Web tool at Kashiwa * Tools stability * Joint meeting wit Busrt search group === 20191107 (Tue.) === * Agenda: * Offline Web tool at Kashiwa * GlitchPlot [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10935|summary slides]] * Tools stability * [[https://www.icrr.u-tokyo.ac.jp/~washimi/KAGRA/PEM/PEMmap/|PEM MAP]], [[https://www.icrr.u-tokyo.ac.jp/~washimi/KAGRA/PEM/KamioKaminari/|KamioKaminari]], [[https://www.icrr.u-tokyo.ac.jp/~washimi/KAGRA/SEM/|Slow Environment Monitors ]] === 20191031 (Tue.) === * Agenda: * Tools stability * Activities on Kashiwa cluster * Talk on f2f meeting === 20191024 (Tue.) === * Agenda: * Tools stability * KGWG activities * PTEP PWT * Minutes: * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10903 === 20191010 (Tue.) === * Agenda: * SummaryPage update * DetChar data server at Kamioka * Data transfer to KISTI (If someone knows the situation) === 20190905 (Tue.) === * Agenda: * SummaryPage updates * Minutes * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10785 === 20190827 (Thu.) === * SummaryPageMeeting20190827 === 20190801 (Thu.) === * Agenda: * Each pipeline status (Omicron, Fscan, Glitch plot…) * Purpose/Goal of the next engineering run === 20190725 (Thu.) === * Agenda * Engineering run results from data analysis * DetChar tool automation plan * update of PEM map [[https://github.com/gw-pem/kagra-pem/issues/159|detail]] === 20190723 (Tue.) === * SummaryPageMeeting20190723 === 20190711 (Thu.) === * Agenda * F2F talk(s) === 20190704 (Thu.) === * Agenda * Kashiwa cluster ([[attachment:DET_Kashiwa_Memo.txt|attachment]]) * Engineering run on Jul. 13th. ([[KAGRA/Subgroups/DET/RUN|link]]) * Data Category flags for BURST. ([[KAGRA/Subgroups/DET/DataQuality|link]], [[https://github.com/gw-detchar/DQConvert|generation script]]) * YuzuSummary ([[https://www.icrr.u-tokyo.ac.jp/~yuzu/bKAGRA_summary/html/GlitchPlot/20190702/1246085661.0_K1:IMC-CAV_TRANS_OUT_DQ.html|sample]]) === 20190613 (Thu.) === * Agenda * Database issue * See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/Meeting/LVK0612|LVK Joint meeting]] * Progresses of Engineering Run analysis * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/RUN|RUN Summary]] * What else * Announcement * TY requested DMG group to create the detchar account on the Kashiwa server. * Data transfer cannot be done due to much amount of data size. So we are now trying to reduce data size. * TY plan to discuss with Kanda-san on next Tue. and Wed. how to transfer the DetChar information. * Mervyn from Fukuoka Univ. plans to come to Kamioka from 25th to 28th Jun. === LVK 20190611/0612 (Tue/Wed) === [[KAGRA/Subgroups/DET/Meeting/LVK0612|Agenda]] === 20190606 (Thu.) === * Agenda * Urgent task for ER with X-arm cavity * Omicron update (Yamamoto) ... Done. * DQ Vector update (Yamamoto). * Glitch visualization (Kozakai) * SummaryPage update (Yokozawa) * Segment file update (Oshino) * Fscan update (Oshino, Yamamoto) === 20190530 (Thu.) === * Agenda * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/Task/O3|Task list for O3 run and Engineering Run on 8th Jun]] * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/DataQuality|Data Quality Flags]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10289|Glitch plot]] === 20190523 (Thu.) === * Agenda * Task list for Engineering Run on 8th Jun. * Trigger based plotting tool [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10253|ckozakai]] === 20190516 (Thu.) === * Agenda * Comment of JRPC meeting and PAB review. * * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|Minutes]] === 20190509 (Thu.) === * Skipped due to the PAB review. === 20190502 (Thu.) === * Skipped due to the Japanese holiday. === 20190425 (Thu.) === * Agenda * SDF preparation * DQ flags for data analysis * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10147|Minutes]] === 20190418 === * Skipped due to the F2F meeting === 20190411 (Thu.) === * Agenda * SDF flags preparation [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9228|slide]] * Fscan on SummaryPage * DetChar computers * Tool development [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10044}|slide]] === 20190404 (Thu.) === * Agenda * IMC run (3/29-3/31, 4/3-4/4) * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10024|yamat]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10029|ckozakai]] * Progress of Kamioka works * hveto * There are some bugs on the latest version of hveto. * Old version of hveto was installed in k1sumX and will be installed in k1det0. * Fscan * Automation of the Scan is already succeeded. * We found a bug in our cache generation system and start to fix this bug. === 20190328 (Thu.) === * Agenda * Progress of Kamioka works * Fscan run on test computer by manually. * For automating and integrating to SummaryPage, we need to generate Segment file in automatically. * We need to consider how to pick up line information and list up it from FScan results. * Automation of hveto on KISTI is succeeded with PMC error signal and PEM channels. * We start to install hveto on hveto@k1sumX. === 20190322 (Fri.) === * --(Zoom3)-- -> Zoom2 (https://zoom.us/j/6676627462) * Agenda * f2f talk * 1 slot (Status talk -> T. Yamamoto) * DAC satellite [?] * Task list in next week * Sharing the current situation of SummaryPage * Preparing k1det0/1 * Managing SDF for VIS * Installing LIGO's tools and KGWG's tools * Task list of engineering run * Providing glitch information: (t, f, SNR) * Providing line information: (f, df, Amplitude, noise source) * Preparing the information server * hveto and glitch identification (Pil-Jong & Kokeyama) * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9984|PMC important channel list]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9258|Glitch analysis presented in JPS]] === 20190314 === * Skipped due to the JPS meeting === 20190307 === * Agenda * Task list of engineering run on May * Tools and results from KGWG * Summary Page isseus * f2f talk === 20190228 === * Meeting room * Zoom3 (https://zoom.us/j/5045179604) * Agenda * Magnetic coupling proposal with LV (Jishnu) * Enhancement of SummaryPage * Data sharing between Kamioka, Kashiwa, and KISTI * Young-Min's trip * Slide * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9903|yamat]] |
----- === Past meeting === * [[KAGRA/Subgroups/DET/Meeting/2023|2023]] * [[KAGRA/Subgroups/DET/Meeting/2022|2022]] * [[KAGRA/Subgroups/DET/Meeting/2021|2021]] * [[KAGRA/Subgroups/DET/Meeting/2020|2020]] * [[KAGRA/Subgroups/DET/Meeting/2019|2019]] |
Meetings
- Meeting time: 11:00-11:30 JST/KST on every Wednesday
- Meeting room: Zoom3
Contents
Agenda & Minutes
20240207 (Wed.)
- Agenda
- Announcement
KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 web
Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 web
- O4a/preO4b(not call it as postO4a)/ER16/O4b schedule:
ER16: It will nominally start on 13 Mar 2024, and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.)
O4b: We plan to commence O4b at 1600 UTC (2500 JST) on 27 Mar 2024.
Ref.internal short announcements (reminders), public announcements
White paper and task list for 2024 git repo
LVK meeting on March 11-14 at Louisiana State University web
- Early Registration is open until February 1
- There is no fee for online participants
Update of member list for DetChar mailing list
- KAGRA site report (Yuzurihara)
- Commissioning support + tasks related to O4a
- O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST
- Event validation (YamaT)
- Online data quality state vector (YamaT)
- Tool to evaluate Gaussianity (Yamamura)
- Scattered light noise (Yamamura)
- Pastavi update (Yuzurihara)
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- Classification of glitch noise (Shikano, Oshino)
- IPC glitch
- line noise study (Samurai)
- Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT)
- DQR update (Yuzurihara)
- Update contents of summary page (Oshino)
- Combine DET computer resources into one DET cluster at Kamioka site
- Related to segment files (Uchikata, Narikawa)
provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) O4a (LV)
- Announcement
- Minutes
20240131 (Wed.)
- Agenda
- Announcement
KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17 web
Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 web
- O4a/preO4b(not call it as postO4a)/ER16/O4b schedule:
ER16: It will nominally start on 13 Mar 2024, and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.)
O4b: We plan to commence O4b at 1600 UTC (2500 JST) on 27 Mar 2024.
Ref.internal short announcements (reminders), public announcements
White paper and task list for 2024 git repo
LVK meeting on March 11-14 at Louisiana State University web
- Early Registration is open until February 1
- There is no fee for online participants
Update of member list for DetChar mailing list
LVK MoA survey summary LIGO DCC
- KAGRA site report (Yuzurihara)
- Commissioning support + tasks related to O4a
- O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST
- Event validation (YamaT)
- Tool to evaluate Gaussianity (Yamamura)
- Scattered light noise (Yamamura)
- Pastavi update (Yuzurihara)
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- Classification of glitch noise (Shikano, Oshino)
- IPC glitch
- line noise study (Samurai)
- Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT)
- DQR update (Yuzurihara)
- Update contents of summary page (Oshino)
- Combine DET computer resources into one DET cluster at Kamioka site
- Related to segment files (Uchikata, Narikawa)
provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) O4a (LV)
- Announcement
- Minutes
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- line noise study (Samurai)
- Is it possible to set the initial parameter in advance, such as prominence and height?
- In future, it is better to extend the fft length to be longer for fine frequency resolution.
- Update contents of summary page (Oshino)
- Related to segment files (Uchikata, Narikawa)
provide the dedicated summary page for O4a of KAGRA (Uchikata and Narikawa) O4a (LV)
- The attempt to generate summary page is on system-B. For reading data, NDS2 server is helpful.
20240124 (Wed.)
- Agenda
- Announcement
- KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17
Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 web
- LIGO-Virgo-KAGRA detchar joint meeting
- tileslot: onthly, 23:00 JST (14:00 UTC) or 6:00 JST (21 UTC)
Last meeting on Nov. 15 23:00 JST (14:00 UTC) wiki
- O4a/preO4b(not call it as postO4a)/ER16/O4b schedule:
O4a: It will end at 1600 UTC on 16 Jan 2024. LLO will end O4a observing early, at 1400 UTC.
ER16: It will nominally start on 13 Mar 2024, and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.)
O4b: We plan to commence O4b at 1600 UTC (2500 JST) on 27 Mar 2024.
Ref.internal short announcements (reminders), public announcements
Information of O4a wiki page
White paper and task list for 2024 git repo
- LVK meeting on March 11-14 at Louisiana State University
Update of member list for DetChar mailing list
- KAGRA site report (Yuzurihara)
- Commissioning support + tasks related to O4a
- O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST
- Event validation (YamaT)
- Tool to evaluate Gaussianity (Yamamura)
- Scattered light noise (Yamamura)
- Pastavi update (Yuzurihara)
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- Classification of glitch noise (Shikano, Oshino)
- IPC glitch
- line noise study (Samurai)
Peak identifications web
- Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT)
- DQR update (Yuzurihara)
- Update contents of summary page (Oshino)
- run Omicron at Kamioka site and refresh the Omicron plots on summary page during O4a period
- Combine DET computer resources into one DET cluster at Kamioka site
- Script to generate segment files (Uchikata, Narikawa)
- Related to segment files (Uchikata, Narikawa)
provide the dedicated summary page for O4a of KAGRA? O3a (LV)
- Announcement
- Minutes
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- Update contents of summary page (Oshino)
20240117 (Wed.)
- Agenda
- Announcement
- KAGRA international workshop (KIW11)@Taiwan: 2023/04/16-17
Gravitaional wave open data workshop (GWODW7)@Taiwan: 2023/04/18-20 web
- LIGO-Virgo-KAGRA detchar joint meeting
- tileslot: onthly, 23:00 JST (14:00 UTC) or 6:00 JST (21 UTC)
Last meeting on Nov. 15 23:00 JST (14:00 UTC) wiki
- O4a/preO4b(not call it as postO4a)/ER16/O4b schedule:
O4a: It will end at 1600 UTC on 16 Jan 2024. LLO will end O4a observing early, at 1400 UTC.
ER16: It will nominally start on 13 Mar 2024, and last for 2 weeks. (Note that ER16 will begin in the middle of the next LVK meeting at LSU, 11-14 March.)
O4b: We plan to commence O4b at 1600 UTC (2500 JST) on 27 Mar 2024.
Ref.internal short announcements (reminders), public announcements
Information of O4a wiki page
White paper and task list for 2024 git repo
- LVK meeting on March 11-14 at Louisiana State University
- KAGRA site report (Yuzurihara)
- Commissioning support + tasks related to O4a
- O4a for KAGRA : 2023/05/25 0:00 JST (=2023/05/24 15:00UTC) ~ 2023/06/21 8:00 JST
- Event validation (YamaT)
- Tool to evaluate Gaussianity (Yamamura)
- Scattered light noise (Yamamura)
- Pastavi update (Yuzurihara)
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- Classification of glitch noise (Shikano, Oshino)
- IPC glitch
- line noise study (Samurai)
Peak identifications web
- Unify conda environment in Kamioka detchar computers, k1sum[01] and k1det[012] (YamaT)
- DQR update (Yuzurihara)
- Update contents of summary page (Oshino)
- run Omicron at Kamioka site and refresh the Omicron plots on summary page during O4a period
- Combine DET computer resources into one DET cluster at Kamioka site
- Script to generate segment files (Uchikata, Narikawa)
- Related to segment files (Uchikata, Narikawa)
provide the dedicated summary page for O4a of KAGRA? O3a (LV)
- Announcement
- Minutes
- Tool to evaluate Gaussianity (Yamamura)
- Gauch recently looks not running. There is no html page linked from summary page. We will check the details later.
- DQR update (Yuzurihara)
- I asked the remote help to Derek. I'm submitteing the application for the ICRR computer account.
- IPC glitch
- Noise hunting by machine learning and Hveto (Kyujin, Kihyun, Syifa)
- The analysis for the remained date will be
- Update contents of summary page (Oshino)
- Tool to evaluate Gaussianity (Yamamura)