Line 3: Line 3:
TBA  * IFI will be purchased from UF
 * Assembly on the PSL table is scheduled in 2014/11
 * Installation will be in 2015/3
 * IFI will not be suspended but directly put on the IFI table
 * A pair of unsuspended steering mirrors (STM) will be used for the beam centering

[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2104|Report by Kentaro]] (2014/1)

[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2486|IFI Layout]] (2014/6)

[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2474|STM noise]] (2014/6)

Input Faraday Isolator

  • IFI will be purchased from UF
  • Assembly on the PSL table is scheduled in 2014/11
  • Installation will be in 2015/3
  • IFI will not be suspended but directly put on the IFI table
  • A pair of unsuspended steering mirrors (STM) will be used for the beam centering

Report by Kentaro (2014/1)

IFI Layout (2014/6)

STM noise (2014/6)